14

1.04 

Unpacking and preparation 

Visual check of lift

Should the packaging be damaged on receipt, each part of LP12 must be 

carefully examined for visible defects or deficiencies. In case of suspected 

damage, do not use the lifting platform until authorised by qualified service 

staff or the Guldmann Service Team.

Preparation of the lifting platform

Charge the batteries of the lifting platform, see under 1.10 on charging.

After charging, the lifting platform is ready for use.

1.05 

Parts list

1.  Lifting platform LP12

2.  Charger

2.00 

Description of functions

2.01 

Labels 

•  Chassis number

•  24 V DC

2.02 

Operation

Operation and indicator light

The lifting platform will be switched on automatically when one of the buttons 

on the control panel is pressed. The green indicator light is switched on when 

the lifting platform is being used. The yellow or red indicator light will be  

switched on 10 to 15 seconds after the last lift has been carried out to indicate 

that the lifting platform is to be recharged.

Working the lifting platform

Unlock the lifting platform with a key 

(pos. 1). Lift up the front edge of the 

access ramp and push it towards the 

back (pos. 2) of the lifting platform, thus 

disengaging the lock which must be 

kept during the operation of the lifting 

platform. 

Then raise the steering handle  

and turn it 90 degrees into steering 

position (pos. 3), release the brakes 

(pos. 4) by pressing down the right 

side of the brake pedal. 

Summary of Contents for Stepless LP12

Page 1: ...1 DK LP12 Løfteplatform 2 GB LP12 Lifting platform 12 S LP12 Lyftplattform 22 ...

Page 2: ...ions 16 2 05 Connecting the charger charging 16 3 00 Transportation 17 3 01 How to transport LP12 17 4 00 Maintenance and Storage 17 4 01 Cleaning 17 4 02 Storage 17 4 03 How to prevent avoid corrosion 17 4 04 What maintenance is required by the owner 18 5 00 Service and Useful Life 18 5 01 Useful Life and Servicing 18 5 02 Battery and Fuses 18 5 03 Inspection All round 18 5 04 Trouble Shooting 19...

Page 3: ...on using your body wieght When turning the lifting platform it can be pulled to reduce the center of rotation Or in places where space is restricted the lifting platform can be pushed to reduce the turning radius 1 03 Important Warnings Do not exceed the max load of 300 kg The lifting platform is built for lifting wheelchair users The lifting platform should only be used on an level surface Always...

Page 4: ...ion and indicator light The lifting platform will be switched on automatically when one of the buttons on the control panel is pressed The green indicator light is switched on when the lifting platform is being used The yellow or red indicator light will be switched on 10 to 15 seconds after the last lift has been carried out to indicate that the lifting platform is to be recharged Working the lif...

Page 5: ...vel with the place of descent and position the access ramp for the descent Loosen the safety belts and descending can now take place Switch off the main power after use by means of the emergency stop to prevent loss of power When in doubt about the use of the lifting platform consult your supplier 2 03 Brakes The brakes are activated by pressing down the left side of the brake pedal and released b...

Page 6: ...ly stop and it will be elevated a little The lifting platform cannot be lowered until the control button UP has been activated If the safety edge is activated when the platform is not in motion the platform will remain on the level on which it was stopped When activating the control button UP the platform will function again 2 05 Connecting the charger charging Connection of charger The charger mu...

Page 7: ...Storage 4 01 Cleaning Clean the lifting platform with a slightly damp cloth or a sponge using ordinary household detergents If the battery box has been removed clean the lifting platform with a soft brush using soapy water Do not rinse the lifting platform with a water hose Dry the lifting platform carefully before mounting the battery again Clean the brakes and other parts on the underside of the...

Page 8: ...and drawings are available from manufacturer or supplier 5 02 Battery and Fuses Change of batteries and fuses should be carried out by a service engineer or by the Guldmann Service Team 5 03 Inspection All round During the inspection a service report shall be made describing what has been checked and exchanged Worn or defective parts shall be replaced by new spareparts from V Guldmann A S 1 Visual...

Page 9: ... arisen finish the inspection 5 04 Trouble Shooting If the LP12 does not react when pressing the keys of the control panel Check that the emergency stop is not activated Check that the batterybox is properly connected Please contact your local Guldmann representative If the green light does not come on when pressing the keys of the hand control Check that the emergency stop is not activated Check t...

Page 10: ... sec No of lifts per charging 45 Pivot radius 2000 mm 79 Total weight of LP12 107 0 kg 235 lbs Electrical connection for charger 230V depending on national voltage standards Connection between charger and hoist 24V DC Charger fully automatic 24V DC 1 Ah Charging time Max 8 hours Batteries gasproof and free of maintenance 2 pcs 12V 7 0 Ah Permitted periodic load 10 90 working time breaks in percent...

Page 11: ...eby declare that Product Lifting platform LP12 Type No XXXXX YYYY ZZZZ x x XXXXX Reference No of the product YYYY Serial No of the product in the production year ZZZZ Production year was manufactured in conformity with the provisions in The Council Directive 98 37 EEC of 22 June 1998 Skejby 01 03 05 Place and day of issue Product responsible Technical Manager Product responsible Technical Manager ...

Page 12: ...Office Graham Bells Vej 21 23A DK 8200 Århus N Tel 45 8741 3100 Fax 45 8741 3131 E mail info guldmann com www guldmann com Guldmann Sverige AB Smålandsgatan 4 S 441 57 Alingsås Tel 46 0322 55290 Fax 46 0322 55320 E mail info guldmann se www guldmann se ...

Reviews: