Prior to installation, check the oil level in the oil
chamber.
Compliance with the
standard EN 60079-14 is
a customer responsibili-
ty.
The pump must be in-
stalled vertically in both
auto-coupling or free-
standing submerged in-
stallation.
Pump installation in pits
must be carried out by
specially trained per-
sons.
Work in or near pits must
be carried out according
to local regulations.
Persons must not work
on the installation area
when the environment is
explosive.
DANGER
Electric shock
Death or serious person-
al injury
‐
It must be possible to
lock the main switch
in position 0. Type
and requirements as
specified in EN
60204-1.
DANGER
Electric shock
Death or serious person-
al injury
‐
Make sure there are
at least 3 m free ca-
ble above the maxi-
mum liquid level.
For safety reasons, all work in pits must be
supervised by a person outside the pit.
Make all maintenance
and service work when
the pump is placed out-
side the pit.
DANGER
Crushing hazard
Death or serious person-
al injury
‐
Make sure that the
lifting bracket is tight-
ened before lifting
the pump.
Carelessness during lifting or transportation may
cause personal injury or damage to the pump.
DANGER
Electric shock
Death or serious person-
al injury
‐
It must be possible to
lock the main switch
in position 0. Type
and requirements as
specified in EN
60204-1.