2
113463_64_65HBC Revision date: 08.27.19
Important Information
READ THIS DOCUMENT BEFORE YOU BEGIN ASSEMBLY
Thank you for purchasing this GrowSpan Roll-Up Pro Tunnel. When
properly assembled and maintained, this product will provide years of
reliable service. These instructions include helpful hints and important
information needed to safely assemble and properly maintain the tunnel.
Please read these instructions
before
you begin.
If you have any questions during the assembly, contact Customer Service
at 1-800-245-9881 for assistance.
SAFETY PRECAUTIONS
• Wear eye protection.
• Wear head protection.
• Wear gloves when handling metal tubes.
• Use a portable GFCI (Ground Fault Circuit Interrupter) when working
with power tools and cords.
• Do not climb on tunnel or framing during or after construction.
• Do not occupy tunnel or attempt to install cover during high winds,
tornadoes, or hurricanes.
•
Never
attempt to install end panels during windy or stormy conditions.
• Assemble and anchor tunnel frame
before
installing cover or panels.
• Do not store hazardous materials in tunnel.
• Provide proper ingress and egress to prevent entrapment.
ANCHORING INSTRUCTIONS
Prior to assembling this high tunnel, please read the
MUST READ
document included with the shipment.
WARNING:
Anchor assembly is an integral part of the high tunnel
construction. Improper anchoring may cause tunnel instability. Failing
to anchor tunnel properly
may void manufacturer’s warranty
and may
cause serious injury and damage.
LOCATION
Choose the proper location for best results. The following suggestions and
precautions will help determine whether the selected location is the best
location.
• Never erect structure under power lines.
• Identify whether underground cables and pipes are present
before
site
preparation or anchoring structure.
• Location should be away from structures that could cause snow to drift
on or around tunnel.
• Do not position tunnel where large loads such as snow and ice, large
tree branches, or other overhead obstacles could fall.
•
Always check local building codes before you begin.
SITE
After choosing a location, prepare the site. The following site characteristics
will help ensure best results.
•
A level site is required
. Site must be level to properly and safely erect
and anchor structure.
• Drainage: Water draining off structure and from areas surrounding
the tunnel should drain away from tunnel to protect tunnel and tunnel
contents.
WARNING:
The individuals assembling this structure are responsible
for designing and furnishing all temporary bracing, shoring, and support
needed during assembly. For safety reasons, those who are not familiar
with recognized construction methods and techniques
must seek the
help of a qualified contractor.