6
STEP 1 VERIFY CONTENTS OF JACKET ASSEMBLY PACKAGE.
Your jacket assembly will contain two (2) manifolds with gaskets, a
fastening package which includes all necessary bolts, screws, nuts
and washers for assembly along with burner studs, nuts and
washers, block insulation, rear of block insulation, aluminum faced
tape, levelling frame rails, two (2) side panels, a rear panel top
panel and re-insulated top and bottom front panels
STEP 2 FRAME RAIL CONNECTION
Attach 10 mm bolts to the underside of the frame rails. These will be used to level the boiler.
Screw the 4 mm jacket affixing screw to the frame rail from the top down. Both the bolt and
affixing screw will be located on the same end of the frame rail. The frame rail will then be
bolted to the legs of the boiler with the frame rail and containing the affixing screw facing in the
direction of the front end of the boiler.
STEP 3 MANIFOLD INSTALLATION
Using the gaskets and bolts supplied connect the manifolds directly to the boiler block. The
top supply manifold will have a 3/4” npt tapping for a relief valve and 1/4” npt tapping for a
gauge. The bottom return manifold has 3/4” npt tapping for a drain vlave. Both manifolds have
1-1/4” male npt threads for sytem connection
.