STEP 8 - FESTOONING INSTALLATION
8.1
If you are using:
Festoon Gliders (Steel Bridges / Runways only)
If you have a monorail go to Step 8.4.
8.2
Slide festoon gliders through end
of
bridge
that corresponds with
festooning on runway. Space
festoon gliders every 3’-0” along
bridge.
8.3
Slide festoon clamp into place at
festooning end of bridge and
tighten clamp bolt (
diagram 8A
).
8.4
Slide festoon gliders into festoon
stack section end of
runway/monorail
track (on
festooning side of
runway/monorail). Space festoon
gliders every 6’-0” along
runway/monorail, between bridge
and festoon stack section.
8.5
Slide festoon clamp into end of runway/monorail/festoon stack section (
diagram 8A
).
Tighten clamp bolt until lockwasher is flat.
8.6
Proceed to Step 8.15, on page 20.
festoon gliders
, go to Step 8.2
festoon trolleys
, go to Step 8.7
Diagram 8A.
Installing festoon clamp on runway or bridge.
18
9/05
Bridge Crane
TIP:
Festoon gliders are comprised of a glider body (with
upper saddle) and lower saddle (a separate piece that
clips onto the glider body).
TIP:
Enough carriers (festoon gliders or festoon trolleys are
supplied to support festoon conductor every 6’ on
runway/monorail and every 3’ on bridges.
Note: