background image

S

TEP 6

S

TEP 5

INSERT T-FITTING THROUGH THE

CUTOUT IN THE WORK SURFACE

FROM THE UNDER SIDE AND ATTACH

TO VAC COVER PORT FROM THE TOP

SIDE BY TIGHTENING THE PIPE

CLAMP WORM GEAR.  REPEAT THIS FOR 

96 AND 108 UNITS THAT HAVE 3 TOP

PORTS.

ATTCH VAC PORT COVERS TO WORK

SURFACE USING PROVIDED SCREWS.

CENTER THE DUCT/COVER OVER THE 

HOLE IN THE COUNTER TOP.

S

TEP 7

INSTALL THE PVC LENGTH

BETWEEN THE 90 ELBOW AND THE

T-FITTING. TO DETERMINE THE LENGTH 

OF PVC REQUIRED, MEAURE THE DISTANCE

BETWEEN THE OUTSIDE EDGES OF THE

WORM GEAR CLAMPS AND ADD 1/4” TO

EACH SIDE. INSERT THE PIPE INTO THE 

FLEXIABLE FITTINGS, CENTER, AND 

TIGHTEN THE WORM GEAR TO SECURE.

REPEAT THIS FOR THE PVC LENGTH BETWEEN

THE TWO T-FITTINGS ON 96 & 108 MODELS

Reviews: