S
TEP 6
S
TEP 5
INSERT T-FITTING THROUGH THE
CUTOUT IN THE WORK SURFACE
FROM THE UNDER SIDE AND ATTACH
TO VAC COVER PORT FROM THE TOP
SIDE BY TIGHTENING THE PIPE
CLAMP WORM GEAR. REPEAT THIS FOR
96 AND 108 UNITS THAT HAVE 3 TOP
PORTS.
ATTCH VAC PORT COVERS TO WORK
SURFACE USING PROVIDED SCREWS.
CENTER THE DUCT/COVER OVER THE
HOLE IN THE COUNTER TOP.
S
TEP 7
INSTALL THE PVC LENGTH
BETWEEN THE 90 ELBOW AND THE
T-FITTING. TO DETERMINE THE LENGTH
OF PVC REQUIRED, MEAURE THE DISTANCE
BETWEEN THE OUTSIDE EDGES OF THE
WORM GEAR CLAMPS AND ADD 1/4” TO
EACH SIDE. INSERT THE PIPE INTO THE
FLEXIABLE FITTINGS, CENTER, AND
TIGHTEN THE WORM GEAR TO SECURE.
REPEAT THIS FOR THE PVC LENGTH BETWEEN
THE TWO T-FITTINGS ON 96 & 108 MODELS