Installation Guide for MRI-1000 

 

GS-08-1724, v 3.2 

Block Diagram

 

 
 
 

 

Summary of Contents for MRI-1000

Page 1: ...served By accepting this material the recipient agrees that the information contained herein will be held in confidence and in trust and will not be used copied or reproduced in whole or in part nor i...

Page 2: ...Installation Guide for MRI 1000 GS 08 1724 v 3 2 2...

Page 3: ...6 Time of Test Phone call 7 Name of Installer 8 Pictures taken of the installation Bracket on pole __________yes no Junction box __________yes no Power meter __________yes no 9 Pictures of the locatio...

Page 4: ...Installation Guide for MRI 1000 GS 08 1724 v 3 2 4...

Page 5: ...Information 1 Safety Information 1 FCC Notice 1 Product Description 1 Installation Procedure 2 Supplies and Equipment Needed for MRI 1000 Installation 3 Installation 4 Block Diagram 5 Installation Pr...

Page 6: ...Installation Guide for MRI 1000 GS 08 1724 v 3 2 ii...

Page 7: ...re designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment This equipment generates uses and can radiate radio frequency energ...

Page 8: ...ted to the PSTN Installation Procedure This procedure covers the installation of the MRI 1000 Outdoor Unit and Junction Box This procedure can be easily adapted to new installations This procedure ass...

Page 9: ...th RJ11 plug o T25 Torx Driver o 1 Phillips Screw Driver o Channel Lock Pliers o inch socket 3 8 or inch drive o in box end wrench o Ratchet Handle same drive as socket o Power Driver or drill motor C...

Page 10: ...re assembly mounts to the pole with two 4 5 inch lag bolts The Cable will run down the pole thru inch EMT Conduit And terminate in a metal enclosure where the Junction Box is mounted along with the kV...

Page 11: ...Installation Guide for MRI 1000 GS 08 1724 v 3 2 5 Block Diagram...

Page 12: ...as best performance will come from overhead thus the less obstruction from surroundings the better 2 The Outdoor Unit contains an antenna that should be at least 5 feet away from other transmitting an...

Page 13: ...dditional conduit as required then add liquid tight Customer provided to the entry point of the enclosure where the junction box will be mounted Run the cable thru this and into the enclosure Install...

Page 14: ...nector into RJ 12 jack inside the Junction Box black cable on right in the picture Route CAT 5 6 Interconnecting Cable through the same gray Gland Nut in side of Junction box gray cable in the picture...

Page 15: ...lling issues in accordance with purchase agreement and or contract provisions LED Should be Green Contact Thomas Babb at Globalstar for Questions concerning the Subscription Activation for the 10 digi...

Page 16: ...use new or refurbished parts and or then current technology for any repairs replacements provided that they maintain form fit function compatibility Customer is to provide Globalstar with notice of th...

Page 17: ...3 Outdoor Unit Serial Number 4 Junction Box Serial Number 5 Color of LED in Junction Box 6 Time of Test Phone call 7 Name of Installer 8 Pictures taken of the installation Bracket on pole __________y...

Page 18: ...Verify That the wire color code matches the legend on the box and that functionally Pin Outs are Pin 1 Orange white Not used Pin 2 Orange Tip Pin 3 Green white Ring Pin 4 Blue 48VDC Pin 5 Blue white 4...

Page 19: ...ld be approximately 50 VDC Using a continuity tool or Telephone Wiring Test Set Verify the connection of two wires all the way from meter to RJ 12 Socket in the Junction Box Verify the continuity of t...

Page 20: ...LEDs should turn on about 60 70 seconds after power is applied to Junction Box They should not stay on for at least 2 minutes 6 Unit fails to answer and connect from the calling test phone Unit not ac...