30
7.3
Scheduled maintenance
The scheduled maintenance operations the manufacturer requires for the LB are
outlined in the table below. The persons performing these operations must have
level 1 Qualification.
FREQUENCY DESCRIPTION
OF OPERATION
PARAGRAPH
8 hours
Cleaning the LB
7.3.1
160 hours
Check safety pin efficiency
7.3.2
! NOTE ! For maintenance of the hydraulic control unit, see the document
supplied by the Manufacturer of that unit.
7.3.1
Cleaning the lift
Using compressed air or a dry brush, carefully clean the entire LB and, in
particular, the areas where the accessories are connected and area for the safety
catches. With a rag, carefully clean the wheel “slide paths” (on the base and on
the frame) and grease lightly with a common grease. Clean the pulling arm with
a rag that is dry or slightly dampened with a detergent solution. Do not use
water.
7.3.2
Checking safety lock status
-
Test the piston that disengages the pawl to ensure that it is properly
activated/deactivated with the “safe release” button (see fig. 5.1).
-
Make certain that the pawl swings freely on its pin.
-
Repeat this operation several times.
7.4
Special or unscheduled maintenance
Special or unscheduled maintenance involves the replacement of some LB
components with reference to the list in Chapter 8. If it proves difficult to replace
or obtain a component, contact the GLOBALJIG Customer Services Department
for information.
! ! WARNING ! !
The use of anything but original, specific spare parts can alter the original
configuration and lead to hazards that cannot be attributed to the LB. GLOBALJIG
cannot be held responsible for any injury or damage to property or the system
itself if non-original parts are used.
Special maintenance operations must be performed by qualified personnel.
Summary of Contents for Evolution
Page 2: ...volution USER S MANUAL Year of Manufacture ...
Page 12: ...10 ...
Page 13: ...11 ...
Page 14: ...12 ...
Page 15: ...13 ...
Page 23: ...21 ...
Page 24: ...22 ...
Page 36: ...34 10 1 Attachment 01 Lift bench dimensions ...
Page 37: ...35 10 2 Attachment 02 Lift bench work area ...
Page 39: ...37 10 4 Attachment 04 Electronic data ...
Page 40: ...38 10 5 Attachment 05 Hydraulic system diagram ...
Page 43: ...41 10 8 Attachment 08 Figures ...
Page 46: ...44 ...