5
INSTALLATION
Please ensure sufficient earthing of the installa-
tion
IMPORTANT!
Follow these instructions when installing ECO 275:
1. Turn off the electricity before opening the unit.
2. Install an airtight water trap in a place without frost-
free to compensate for the fan pressure.
3. The water trap must have a height of at least 50 mm.
4. Ensure that the condensate drain has a sufficient slope
(at least -1%) towards the sewer.
5. Pour 1 litre of water into the condensate tray of the unit
to check that it drains correctly. Make sure the conden-
sate drain is filled with water before each heating
season.
6. If the condensate drain is exposed to frost, a thermo-
stat and an electric tracing device must be installed to
prevent the drain from freezing when the temperature
drops below +2°C.
7. Before commencing operation, adjustments must be
made on both the supply and exhaust air. It is important
to ensure a balance between the amounts of intake and
exhaust air.
8. We recommend that you keep the ventilation ducts
closed until the unit is started and the system is cali-
brated.
These instructions must be followed.
If the installation is
not carried out in accordance with these instructions,
KVM-Genvex cannot be held liable for any potential further
damage that extends beyond the Genvex unit.
KVM-Genvex A/S always recommends careful planning of
the installation space for your Genvex product in relation to
the location of living spaces. As this is a technical product
that contains fans and/or a heat pump, in rare cases, and in
combination with inappropriate installation conditions, it
may cause unsatisfactory noise or vibration nuisance. As a
general rule, it is always recommended to install the
technical system so that it is not located in the immediate
vicinity of a bedroom. Furthermore, when securing the
Genvex unit to the building structure, it is recommended
attaching it to a heavy structural component such as
concrete. It should also be ensured that no sound or vibra-
tions can be transmitted through materials in contact with
the technical system. If there is a risk of propagation of
noise and vibrations, further installation of vibration-damp-
ing material and sound-damping of installation rooms are
recommended.
Wall mounting
Before starting the installation of the ventilation unit
Make sure that the wall used to hold the ventilation unit is
built in such a way that it is able to support the weight of
the unit. In addition, the wall must be straight and plumb.
ECO 275 comes with a pre-installed wall bracket as shown
in Figure 1
Before mounting the ECO 275, install a total of 3 Ø6-8 mm.
bolts into the wall. The bolts should be installed level
according to the dimensions as shown in Figure 1.
After installing the bolts, hang ECO 275 onto the bolts
using the keyholes in the wall bracket.
The unit must be mounted level to ensure drainage from the
condensate tray. If necessary, use the adjusting screw on
the back of the unit to adjust the position of the unit.
8
12
,5
15
262
262
Figure 1