Part No. 43063
Genie Z-30/20
7 - 11
Service Manual - Third Edition
Section 7 - Repair Procedures
3-1
Plastic Cable Track
The primary boom cable track guides the cables
and hoses running up the boom. It can be repaired
link by link without removing the cables and hoses
that run through it. Removing the entire primary
boom cable track is only necessary when
performing major repairs that involve removing the
primary boom.
How to Repair the Plastic Cable
Track
Component damage hazard. The
primary boom cable track can be
damaged if it is twisted.
a
link separation point
b
lower clip
1 Use a slotted screwdriver to pry down on the
lower clip.
2 Repeat step 1 for each link.
3 To remove a single link, open the lower clip
and then use a screw driver to pry the link to
the side.
a
b
3-2
Primary Boom
How to Shim the Primary Boom
Measure each wear pad. Replace
the wear pad if it is less than
0.41 inches (1 cm) thick. If the
wear pad is more than 0.41 inches
(1 cm) thick, perform the following
procedure.
1 Extend the boom until the wear pads are
accessible.
2 Loosen the wear pad mounting fasteners.
3 Install the new shims under the wear pad to
obtain zero clearance and zero drag.
4 Tighten the mounting fasteners.
5 Extend and retract the boom through an entire
cycle. Check for tight spots that could cause
scraping or binding.
Always maintain squareness
between the outer and inner boom
tubes.
How to Remove the
Primary Boom
This procedure requires specific
repair skills, lifting equipment and
a suitable workshop. Attempting
this procedure without these skills
and tools may cause death or
serious injury and significant
component damage. Dealer
service is strongly recommended.
Perform this procedure with the
boom in the stowed position.
1 Remove the platform. See 2-1,
How to Remove the Platform.
2 Disconnect the battery pack plugs from the
machine.
3 Remove the turntable covers.