12
12.) Power on unit and check for leaks in duct work. All leaks should be sealed with Aluminum tape
and insulated.
Hard Wiring Instructions
Figure 3: Hard Wiring Diagram
Caution:
To reduce the potential of electric shock or fire, the wiring required by this manual should be
performed by a licensed electrician in accordance with applicable National Electric Code, NFPA 70,
and local codes.
•
Have an electrician run 120V AC power to the location of the DT-FP unit and install a junction
box. Use a minimum of 16 AWG cable. 14 AWG is preferable.
•
Disconnect the power running to the junction box at the building fuse box before wiring.
•
Cut Plug off DT-FP power cord. Peel off insulation to expose wires. Run power cord to the
junction box.
•
Use wire nuts to connect the ends of the power cord to the leads in the junction box. Line to
line (Black), neutral to neutral (White), and ground to ground (Green).
•
Reconnect power once all wires have been connected and exposed wire has been insulated.