4. Use the manual transfer handle inside the trans-
fer switch to move the main contacts to their
“Standby” position, i.e., loads connected to the
standby power source (Figure 3.2).
5. To crank and start the engine, set the AUTO/OFF/
MANUAL switch to MANUAL.
6. Let the engine stabilize and warm up for a few
minutes.
7. Set the generator’s main circuit breaker to its ON
(or closed) position. The standby power source
now powers the loads.
Figure 3.2 – Manual Transfer Switch Operation
3.5.2
TRANSFER BACK TO UTILITY POWER
SOURCE
When utility power has been restored, transfer back
to that source and shut down the generator. This can
be accomplished as follows:
1. Set the generator’s main circuit breaker to its
OFF (or open) position.
2. Let the engine run for a minute or two at no-load
to stabilize the internal temperatures.
3. Set the generator’s AUTO/OFF/MANUAL switch
to its OFF (or open) position. The engine should
shut down.
4. Check that utility power supply to the transfer
switch is turned OFF.
DANGER
Do not attempt to activate the transfer switch
manually until all power voltage supplies to the
switch have been positively turned off. Failure
to turn off all power voltage supplies may result
in extremely hazardous and possibly fatal elec-
trical shock.
5. Use the manual transfer handle inside the trans-
fer switch to move the main contacts back to their
“Utility” position, i.e., loads connected to the util-
ity power source (Figure 3.2).
6. Turn ON the utility power supply to the transfer
switch using the means provided.
7. Set the system to automatic operation as outlined
in “Automatic Transfer Operation,” Section 3.3.
3.6 SETTING THE EXERCISE TIMER
The generator is equipped with an exercise timer.
Once it is set, the generator will start and exercise
once every seven days, on the day of the week and at
the time of day the following sequence is completed.
During this exercise period, the unit runs for approx-
imately 12 minutes and then shuts down. Transfer of
loads to the generator output does not occur during
the exercise cycle.
A switch on the control panel (see Figure 3.1) permits
selection of the day and time for system exercise. To
select the desired day and time of day, the following
sequence must be performed at that time.
1. Verify that the AUTO/OFF/MANUAL switch is set
to AUTO.
2. Hold down the set timer switch until the genera-
tor starts (approximately 10 seconds) and then
release.
3. The generator will start and run for approximately
12 minutes and then shut down on its own. The
exerciser will then be set to run at that time of day
every week.
NOTE:
The exerciser will only work in the AUTO mode
and will not work unless this procedure is per-
formed. The exerciser will need to be reset every
time the 12-volt battery is disconnected and then
reconnected. The exerciser WILL NOT work if
dip switch 2 (Remote Not Auto) on the controller
printed circuit board is ON.
3.7 PROTECTION
SYSTEMS
3.7.1 LOW OIL PRESSURE SWITCH
This switch (Figure 3.3) has normally closed con-
tacts that are held open by engine oil pressure during
cranking and operating. Should oil pressure drop
below the 8 psi range, switch contacts close, and the
engine shuts down. The unit should not be restarted
until oil is added, and the AUTO/OFF/MANUAL switch
must be turned to OFF and then back to AUTO.
Section 3 — Operation
Air-cooled 7 kW, 12 kW and 15 kW Generators
16