Page 18 Edition I
03.12.2012
11.
Power failure.
After a power failure, the controller will start operations according to the state it was in before
the power failure. The controller will wait for one minute to allow the power supply to stabilise,
and will then continue to operate according to pre-programmed parameter values. While waiting,
the display shows the time in seconds remaining until operations with pre-programmed parameter
values begin again.
12.
Room thermostat.
12.1
GA01HC room panel.
The GH07EB controller is designed for full communication with the GECO GA01HC room
panel, which allows monitoring of the boiler from the comfort of your apartment.
Connecting the GH07EB controller to the GA01HC room panel allows:
•
Changing the boiler output temperature
•
Changing the temperature of water returning to the boiler
•
Changing the DHW temperature
•
Display of all alarms in text form
•
Overview of boiler operations
•
Overview of operations of connected devices (electrode boiler, CH pump, DHW pump)
•
Overview of all temperature measurements
If the GH07EB electrode boiler controller is connected to the GA01HC-01 room panel, this
will be detected automatically by the controller and activation does not require any additional
steps or settings from the user. Once connected, the boiler controller operates according to the
room panel settings. Disconnection or damage to the cable connecting the panel and the controller
will result in the light behind the icon Disconnection or damage to the cable connecting the panel
and the controller will result in the light behind the icon
on the GA01HC room panel going
out.
Correct connection with the controller is signalled by a lit LED behind
the
icon on the GA01HC room panel