Starting for the first time
Initial commissioning checklist
2008-9015-001
01-2017
6.3
Initial commissioning checklist
This checklist must be completed by the dealer and the customer. The initial
commissioning steps intend to test the product to validate its functionality.
Therefore, the dealer and the customer must operate the product to make sure
the product is assembled and/or installed according to the manufacturer's
instructions.
General
DONE
N/A
The owner received the instruction manual from the dealer and commits to read it.
The owner is instructed by the dealer on how to operate and maintain the product.
The safety labels are installed.
The lubrication points are lubricated.
All bolts are torqued.
All connections are secured.
A visual inspection is performed to ensure there are no leaks, signs of distortion or defective parts.
The equipment/component provided by the owner comply with the specifications contained in section
Technical data.
The motor belts tension is adjusted.
The pulley hubs are secured with a set screw.
The belts safety guard is installed and bolted.
Both motor pulleys are aligned and parallel.
The pump rotates in the proper direction.
The control panel is connected to an external cut-off switch.
The pump can be shut down only through the control panel cut-off switch.
Note!
The dealer and the owner must fill the warranty registration form when
the checklist is completed.
Dealer's signature:
______________________________________________________________
Owner's signature:
______________________________________________________________
Date:
______________________________________________________________