Customer Name:

PMI Name:

GON/SO Number:

Field Service Name:

Equipment:

Country/City or City/State:

Required site assessment milestones

Date of completion (dd/mm/yyyy)

1) Check site before Magnet Delivery

2) Check site before installation start

Place an "X" in either Y or N column

Site Ready Checks at Installation

Y

N

General Site Planning

Room dimensions, including ceiling height, for all Exam, Equipment/Technical & Control rooms meets GE specifications.

Ceiling support structure, if indicated on the GE drawing, is in the correct location and at the correct height according to the

of any GE supplied components. Overhead support Structure has been confirmed with customer/contractor to meet required
GE provided criteria.

Rooms that will contain equipment, including staging areas if applicable, are construction debris free. Precautions must be

taken to prevent debris from entering rooms containing equipment.

Finished ceiling is installed. If applicable ceiling tiles installed per PMI discretion.

Adequate delivery route from truck to final place of installation has been reviewed with all stakeholders, all
communications/notifications have occurred, arrangements have been made for special handling (rigging, elevator, fork lift,
etc.). All floors along delivery route will support weight of the equipment, temporary reinforcements arranged if needed.

System power & grounding (PDB/MDP) is available as per GE specifications, installed at point of final connection and ready to
use. Lock Out Tag Out is available.

System power and grounded audit has been scheduled to be completed during installation of equipment. (If Required) GEHC
PM to confirmed if needed.

Adequate room illumination installed and working.

Cable ways (floor/wall/ceiling/Access Flooring) are available for installation of GE cables and are of correct length and
diameter. Cable ways routes per GE Final drawings and cable access openings areas installed at a time determined by GEHC
PM. Surface floor duct can be installed at time of system installation.

HVAC systems Installed, and the site meets minimum environmental operational system requirements.

Network outlets installed and computer network available and working.

Hospital IT/connectivity contacts have been engaged and information has been added to Project management tool. (If
Required)

Floor levelness/flatness is measured and within tolerance, and there are no visible defects per GEHC specifications. Floor
Strength and thickness have been discussed with customer/contractor and they have confirmed GE requirements are met.

Customer supplied countertops where GE equipment will be installed are in place.

Specific for MR

RF Shield installed with possible exception of magnet entrance. RF Shield Effectivity and Ground Isolation Test needed. If GE
responsible for supplying RF shield, the RF shield Effectivity and Ground Isolation Test data is a Mandatory attachment into
MyProjects.

Power and connectivity is available for magnet monitoring.

Delivery route for He dewars & gradient coil cart to the scanning room is available.

Chilled water supply for Water Cooled Compressor or Air Cooled Compressor is ready and meets GE specifications.

Water drain available in the equipment room, if applicable.

Power for MR compressor & Chiller is available.

Ensure cryogen venting system is available for magnet connection.

Exhaust fan system is installed and operational per GE requirements.

Status of work

General comments

System can be delivered

PMI signature

Site ready for installation

FS signature: optional

GLOBAL SITE READINESS CHECKLIST (DI)

DOC1809666 Rev. 5

GENERAL SPECIFICATIONS

GE is not responsible for the installation of developers and associated equipment, lighting, cassette trays and
protective screens or derivatives not mentioned in the order.
The final study contains recommendations for the location of GE equipment and associated devices, electrical
wiring and room arrangements. When preparing the study, every effort has been made to consider every
aspect of the actual equipment expected to be installed.
The layout of the equipment offered by GE, the dimensions given for the premises, the details provided for
the pre-installation work and electrical power supply are given according to the information noted during
on-site study and the wishes expressed by the customer.
The room dimensions used to create the equipment layout may originate from a previous layout and may not
be accurate as they may not have been verified on site. GE cannot take any responsibility for errors due to
lack of information.
Dimensions apply to finished surfaces of the room.
Actual configuration may differ from options presented in some typical views or tables.
If this set of final drawings has been approved by the customer, any subsequent modification of the site must
be subject to further investigation by GE about the feasibility of installing the equipment. Any reservations
must be noted.

customer's responsibility to ensure that the site and final equipment placement complies with all applicable
local requirements.
All work required to install GE equipment must be carried out in compliance with the building regulations and
the safety standards of legal force in the country concerned.
These drawings are not to be used for actual construction purposes. The company cannot take responsibility
for any damage resulting therefrom.

CUSTOMER RESPONSIBILITIES

It is the responsibility of the customer to prepare the site in accordance with the specifications stated in the

final study. A detailed site readiness checklist is provided by GE. It is the responsibility of the customer to
ensure all requirements are fulfilled and that the site conforms to all specifications defined in the checklist and

up and ensure that actions in the checklist are complete, and if necessary, will aid in the rescheduling of the
delivery and installation date.
Prior to installation, a structrual engineer of record must ensure that the floor and ceiling is designed in such a
way that the loads of the installed system can be securely borne and transferred. The layout of additional
structural elements, dimensioning and the selection of appropriate installation methods are the sole
responsibility of the structural engineer. Execution of load bearing structures supporting equipment on the
ceiling, floor or walls are the customer's responsibility.

DISCLAIMER

THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.

DATE

NAME

SIGNATURE

Date

Rev

/24

EN-MRI-TYP-SIGNA_PIONEER-WEB.DWG

A

23/Jul/2018

SIGNA PIONEER

Typical

C2 - Disclaimer - Site Readiness

02

Summary of Contents for SIGNA PIONEER

Page 1: ... set of final issue drawing GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings however caused All dimensions are in millimeters unless otherwise specified Do not scale from printed pdf files GE accepts no responsibility or liability for defective work due to scaling from these drawings 24 EN MRI TYP SIGNA_PIONEER WEB DWG PMM 5680003 1EN 1 4 1 0 23 Jul ...

Page 2: ...om if applicable Power for MR compressor Chiller is available Ensure cryogen venting system is available for magnet connection Exhaust fan system is installed and operational per GE requirements Status of work General comments System can be delivered PMI signature Site ready for installation FS signature optional GLOBAL SITE READINESS CHECKLIST DI DOC1809666 Rev 5 GENERAL SPECIFICATIONS GE is not ...

Page 3: ...contained to the magnet room If not possible a barrier is recommended to prevent entry to the 5g field area 2 The spaces around above and below the magnet must be reviewed for effects of the 5g 3g 1g and 5g fields Refer to the proximity limit chart in the MR pre installation manual referenced on the cover sheet 3 For moving metal the restriction lines typically extend outside of the MR space Pleas...

Page 4: ...width C 25 Minimum opening for is 43 in w x 82 in h contingent on a 96 in corridor width C 26 Counter top for equipment provide grommeted openings as required to route cables C 27 Base cabinet for storage of surface coils patient positioning pads phantoms etc C 28 Louvered doors refer to preinstall for requirements C 29 Magnet access 9 0 x10 0 C 30 Shelf LEGEND A GE Supplied C Customer contractor ...

Page 5: ...LD Note Define RF shield s inset according to provisions made by the RF Shield vendor Warning 5 Gauss line outside the Magnet room limits MAGNET ROOM CONTROL ROOM FRONT VIEW WITH MAGNETIC FIELD 4 3 2 1 1 2 9 MAGNET ROOM Note Define RF shield s inset according to provisions made by the RF Shield vendor Warning 5 Gauss line outside the Magnet room limits 8 9 TBD TBD 8 9 TBD TBD 3 6 3 6 8 9 8 9 ...

Page 6: ...dry equipment Food preparation area Water cooling equipment HVAC equipment Major mechanical equipment room Credit cards watches and clocks Air conditioning equipment Fuel storage tanks Motors greater than 5 horsepower 50 gauss 5mT Metal detector for screening LCD panels Telephones No Limit Digital Detectors Acoustic and vibroacoustic information is provided for site planning and architectural desi...

Page 7: ...ew INTEGRATED COOLING CABINET Top View PENETRATION PANEL CLOSET An enclosure i e closet must be provided to restrict access to the PEN panels and for storage of excess interconnections The PEN closet must have a mechanical locking mechanism to restrict access to the PEN panels The PEN closet must maintain the minimum service area outside the 200 Gauss in the magnet room PEN closet must allow free ...

Page 8: ...n 150 5 9 in 1130 44 5 in 860 33 9 in 340 13 4 in 825 32 5 in Service clearance Cable drop area Cover 150 70 0 5 9 in 2 8 in 0 in 300 11 8 in 388 15 3 in 800 31 5 in 907 35 7 in 3674 144 7 in SIDE VIEW TOP VIEW NOT TO SCALE PATIENT TABLE PT Center of gravity MAGNET ENCLOSURE Note Center of gravity is approximate and includes the GE Healthcare supplied VibroAcoustic Dampening Kit but does not inclu...

Page 9: ...of Gravity SCALE 1 10 TOP VIEW FRONT VIEW SIDE VIEW 194 7 64 in 401 15 79 in 755 29 71 in 308 12 13 in 700 27 56 in 335 5 13 21 in Date Rev 24 EN MRI TYP SIGNA_PIONEER WEB DWG A 23 Jul 2018 SIGNA PIONEER Typical A7 Equipment Details 2 09 ...

Page 10: ...e allow the equipment to be delivered If the site is not ready GE can delay the delivery time Recommended minimum opening for side wall delivery 2500 98 5in width x 2500 98 5in height PATH WITH 90 DEGREE TURN FRONT VIEW OF MAGNET RIGHT SIDE VIEW OF MAGNET STRAIGHT PATH Rigging wheels required GRADIENT COIL REPLACEMENT The weight bearing structure of the site should support any additional weight of...

Page 11: ...uld be given to the selection of light fixtures cabinets wall decorations etc To minimize this potential hazard For safety all removable items within the magnet room such as faucet handles drain covers switch box cover plates light fixture components mounting screws etc Must be non magnetic If you have a specific question about material bring it to the attention of your GE project manager of insta...

Page 12: ...ED INSTALLED 3 Patient table dock anchoring 4 Structural wall backing for Main Disconnect Panel 5 Structural wall backing for Magnet Rundown Unit Date Rev 24 EN MRI TYP SIGNA_PIONEER WEB DWG A 23 Jul 2018 SIGNA PIONEER Typical S2 Structural Layout 12 MAGNET ROOM EQUIPMENT ROOM CONTROL ROOM 4 5 3 1 1 1 1 5 2 17 3 9 4 11 6 6 4 9 4 LOCATED ELSEWHERE ...

Page 13: ...ement cart throughout operation and service life Floor must be flat and level to 3 mm 0 12in between high and low spots over the area shown 3419mm 134 61in 943mm 37 13in PATIENT TABLE DOCK ANCHOR MOUNTING REQUIREMENTS The RF Shield vendor must design and install the dock anchor bolt The dock anchor hole must be drilled after the Magnet is installed The dock anchor must not contact floor rebar or o...

Page 14: ...supports hoses clamps ventlation systems etc are to be supplied and installed by the customer or his contractors For complete design and requirements specifications and guidelines refer to the pre installation manual system cooling cryogen venting waveguides and exhaust venting An emergency water cooling back up supply is recommended for continuous cryogen compressor operation if using an open loo...

Page 15: ...hes in parallel Ductwork Ductwork MAGNET ROOM VENTING REQUIREMENTS HVAC VENT REQUIREMENTS HVAC vendor must comply with Magnet room temperature and humidity specifications and RF shielding specifications RF Shield vendor must install open pipe or honeycomb HVAC waveguides All serviceable parts in the Magnet room e g diffusers must be non magnetic Waveguides must be nonmagnetic and electrically isol...

Page 16: ... emergency backup facility coolant For the site without insite connection the customer must provide and install an in line thermometer on the supply MAGNET ROOM Integrated System Cabinet ISC EQUIPMENT ROOM CUSTOMER SUPPLIED Water Cooling Water Cooling Return Supply Magnet MAG Gradient Coil VRMw RF Shield Integrated Cooling Cabinet ICC Patient Air Cooling FLOWMETER 100 micron FILTER Facility Plumbi...

Page 17: ... in KEY COMPONENTS RF waveguide extended from wall to magnet adapter Must be all same material and all welded Support system must withstand 11125 N 2500 lbs GE ventglas must be installed in vertical section directly over magnet TYPICAL CRYOGENIC VENT PIPE DETAIL MAGNET VENT ADAPTER Do not remove or modify the vent adaptor bolted to the magnet VENT PIPE 610 mm 24 in may be cut to a minimum of 100 m...

Page 18: ...24 39 30 49 0 088 1 991 0 86 5 20 0 57 3 93 1 60 11 06 1 07 7 37 3 21 22 12 14 in 350mm 0 20 0 00 6 10 0 008 0 180 0 123 0 85 0 082 0 57 0 231 1 59 0 154 1 06 0 462 3 18 20 40 6 10 12 22 0 017 0 380 0 206 1 42 0 137 0 95 0 386 2 66 0 257 1 77 0 771 5 32 40 60 12 22 18 29 0 024 0 552 0 281 1 94 0 187 1 29 0 525 3 62 0 350 2 42 1 051 7 25 60 80 18 29 24 39 0 031 0 699 0 349 2 41 0 232 1 60 0 652 4 5...

Page 19: ...c must run direct as possible otherwise may result in the need for greater than standard cable lengths refer to the interconnection diagram for maximum usable lengths point to point 8 Conduit turns to have large sweeping bends with minimum radius in accordance with national and local electrical codes 9 A special grounding system is required in all procedure rooms by some national and local codes I...

Page 20: ... SUPPLIED INSTALLED 1 Cable ladder 450mm x 150mm 18 x 6 2 Non ferrous cable ladder 450mm x 150mm 18 x 6 3 Box above ceiling size per local code 4 150mm x 100mm 6 x 3 1 2 Surface wall duct 5 100mm x 100mm x 50mm 4 x 4 x 2 J Box 6 Main disconnect panel 7 One 50mm 2 cnd above ceiling 8 One 75mm 3 cnd above ceiling 9 Breaker Boxes ITEM QTY Outlet Legend for GE Equipment System emergency off SEO recomm...

Page 21: ...YP SIGNA_PIONEER WEB DWG A 23 Jul 2018 SIGNA PIONEER Typical E3 Electrical Elevations 21 MAGNET ROOM EQUIPMENT ROOM 8 9 TBD TBD 1 MAX 10 8 MIN 0 10 4 4 3 CONTROL ROOM 10 8 MAXIMUM 5 4 5 4 5 5 2 TBD TBD TBD TBD TBD TBD 6 5 5 0 7 ...

Page 22: ...8 in 6 Minimum distance from top of cable tray to ceiling 254 mm 10 in Minimum distance on either side of an obstruction 254 mm 10 in minimum distance from top of cable tray to Obstruction 178 mm 7 in 9 Minimum distance between trays 12 mm 0 5 in 10 Non ferrous cable support center Cable Tray Requirements Side By Side 1 6 5 10 8 9 11 CABLE TRAYS IN EQUIPMENT ROOM CABLE TRAY DETAIL NOT TO SCALE Min...

Page 23: ...kVA STAND BY POWER 17kVA SPECIFICATIONS OF MAIN POWER INPUT CABLES Power and cable installation must comply with the distribution diagram Size of the Main power input cable is determined by the customer taking its length and admissible voltage drops into consideration All cables must be isolated and flexible cable color codes must comply with standards for electrical installation The cables from s...

Page 24: ...NG FOR OPTIONS OPTION FROM TO CABLE LENGTH m ft MRE MRE Magnet Isocenter Nominal 7 31 24 Maximum 10 06 33 MRE ISC cabinet 15 24 50 MRE Ethernet Hub in ISC 15 24 50 MRE Customer Supplied Outlet 60 Hz 6 09 20 50 Hz 7 62 25 9 40 m 30 8 ft 25 00 m 82 ft 5 40 9 40 m 17 5 30 8 ft 24 70 m 81 ft 16 80 m 55 ft 16 40 m 53 8 ft 0 40 6 40 m 1 3 21 ft 13 00 m 42 7 ft 25 00 m 82 ft 24 4m 80 ft 29 8m 97 7 ft Dat...

Reviews: