background image

DEH40212 Installation Instructions

3

TO RELAY

RR7P RELAY SHOWN

LED INDICATOR

RELAY
CONTROL
BUTTON

POWER UP AND TEST RELAYS

1.

Apply power to the power supply only.

 As shown in

Figure 3

, to the right, press the Relay Control Button next

to each relay’s yellow plug-in termination to toggle it ON/
OFF. The relay should “click” and the LED status indicator
should change state. Confirm the operation by measuring
the continuity at the line-voltage terminations of each
relay.

2.

Apply power to the relays.

 Being careful not to touch

any line-voltage wiring, toggle each relay ON/OFF again
and confirm that each relay controls the appropriate load.

Record the circuit controlled by each relay on the 

RELAY

SCHEDULE 

which was shipped with the interior. The relays

DOCUMENT RELAY WIRING

Figure 3

associated with automation channels A-H are recorded later.

Each ProSys panel includes eight “channels” (A-H) which may
be softwired to relays within the panel. Channels are used to
group relays for common control.

When a ProSys system includes an automation module
(RCLK8PS Softwired Clock), we strongly recommend you turn
to the installation instructions for that automation module and

complete the documentation before softwiring any
relays to channels

.

However, if automation is to be provided by an interface to
another system, or by using manual switches only, the
channels may be used simply for grouping relays. Follow the
instructions in 

Figure 5

 to the left.

SOFTWIRING A RELAY GROUP TO A CHANNEL

RELAY #

SUPPLY

LOAD DESCRIPTION

-01

LP1-1

OPEN OFFICE - FIRST FLOOR NW

-02

LP1-2

                        "

-03

LP1-3

OPEN OFFICE - FIRST FLOOR NE

-04

LP1-4

                        "

-05

LP1-5

OPEN OFFICE - FIRST FLOOR SW

PROSYS RELAY SCHEDULE

Figure 4

PANEL #

01

1 Press and hold the

Channel Push Button
for several seconds.

2 Select the relays to

be controlled.

3 Press the Channel

Push Button again.

Test. Press the
Channel Push Button
to toggle the group
ON/OFF/ON.

Figure 5 – Softwiring a Relay Group

3

2

PRESS
AND
HOLD
CHANNEL
PUSH
BUTTON

FLASHING 
LED

FLASHING 
RED LED

H

H

H

H

Summary of Contents for ProSys DEH40212

Page 1: ... the Dataline 3 Document the Relay Panels Full descriptions of the installation and operation of Softwired Switches and the Softwired Clock and other optional automation devices are located in other sections of this manual and are provided with each hardware unit Before starting read the following installation instructions If you have questions call GE Total Lighting Control Service at 1 877 584 2...

Page 2: ...earance Pulling Wires Route line voltage wiring through the 21 2 knockouts in either the top or bottom of the tub Route Class 2 low voltage dataline from the remote switches or other controls through the 3 4 knockouts in either end Install Interior Power Supply Attach the power supply to the frame bottom of 12 relay interior and left side of 24 or 48 relay interiors and plug the low voltage connec...

Page 3: ... may be softwired to relays within the panel Channels are used to group relays for common control When a ProSys system includes an automation module RCLK8PS Softwired Clock we strongly recommend you turn to the installation instructions for that automation module and complete the documentation before softwiring any relays to channels However if automation is to be provided by an interface to anoth...

Page 4: ... panel address is set higher than 30 the channel LEDs in the panel will flash Setting the panel address to 30 or below will return the panel to normal operation If a panel is set to the same address as another panel then the two panels will not operate properly The ProSys LM panels can be setup in groups of 30 where the panels in a group can be numbered from 00 to 30 Note To ensure good communicat...

Page 5: ...uld be tested for continuity and isolation from ground To test for continuity remove the red and black dataline wires at panel 01 and wire nut together short the wires together Go to the last panel in the series and measure the resistance between the red and black terminals It should be less than 3 ohms Return to panel 01 and restore the red and black wires to their associated terminals For shorts...

Page 6: ...6 DEH40212 Installation Instructions GE Total Lighting Control 41 Woodford Avenue Plainville CT 06062 2000 General Electric Company GE Total Lighting Control DEH40212 BL 0700 R02 ...

Reviews: