RELAY PANEL INSTALLATION

CAUTION: Make sure all power is OFF before wiring.
Do not energize wiring until the unit is fully assembled.
Conform to all applicable codes.

ILLUSTRATION NOT TO SCALE

If you have purchased the ProSys II Lighting Control System
(the stand-alone system), the devices (panels, switches and
clock) will be in self-install mode, which means that as soon
as they are connected to the network, they are operational
and can communicate with each other.

If you have purchased the ProSys LM Lighting Control System
along with the ProSys LM software, the devices will be in
software-install mode. This means that in order for them to
function on the network you must:
• assign network addresses to the devices and
• bind network variables and message tags using your
   network management tool.

Addresses and binding are necessary for the devices to function on
the network. ProSys LM users please refer to the ProSys LM
Software User Guide for instructions on installing devices.

Rough-In Tub

• Environment

32 to 131

o

F (0 to 50

o

C), 0 to 95% relative humidity,

stationary applications

• Mounting

The tub should be level, plumb and rigidly installed with
hardware sufficient to hold 100 lbs. (48kg). For flush-mount
panels, the front flange should be flush with the final
finished surface. For multiple panels, allow 

1

4

” minimum

between panels for showbox cover clearance.

• Pulling Wires

Route line-voltage wiring through the 2

1

2

” knockouts in

either the top or bottom of the tub. Route Class 2 low-
voltage dataline from the remote switches or other controls
through the 

3

4

” knockouts in either end.

Install Interior

•  Power Supply

Attach the power supply to the frame (bottom of 12-relay
interior and left side of 24- or 48-relay interiors) and plug
the low-voltage connector to the terminal marked “POWER”
as shown in 

Figure 1

 above.

• Interior

Mount the interior in the tub and secure it to the studs with
the hardware provided. Make sure that all line- and low-
voltage wiring is confined to the appropriate areas.

Wire Line Voltage

Before making any connections to the relays, make sure that
none of the load circuits are shorted. Wire from the circuit
breaker through each relay’s SPST output terminals, and from
there to the loads. Confirm that each circuit is wired to the
relay specified in the drawings. Wire the power supply.

RINTER2424PS

shown

B

A

C

C

2" TYP.

SWITCHED LIGHTING CIRCUITS

CLASS 2

LOW-VOLTAGE

WIRING SECTION

LINE-VOLTAGE WIRING SECTIONS

5" WIDE

1.5" x 1.5" CROSSOVER WIRING CHANNEL (TOP AND BOTTOM)

CIRCUIT BREAKER PANEL

RELAYS

RELAYS

DIN RAIL

4.5" D

Dimensions (A x B)

RINTER1212PS(P)
16.0" (406mm) x 16.5" (419mm)

RINTER2424PS(P)
22.5" (572mm) x 24.0" (610mm)

RINTER4848PS(P)
36.0" (914mm) x 24.0" (610mm)

Relay Capacities (C)

RINTER1212PS

12 RR7 relays

RINTER1212PSP

12 RR9 relays

RINTER2424PS

24 RR7 relays

RINTER2424PSP

24 RR9 relays

RINTER4848PS

48 RR7 relays

RINTER4848PSP

48 RR9 relays

DIN Rail Capacities

RINTER1212PS(P)

One module

RINTER2424PS(P)

Two modules

RINTER4848PS(P)

Two modules

Figure 1

Figure 2

Summary of Contents for ProSys DEH40212

Page 1: ... the Dataline 3 Document the Relay Panels Full descriptions of the installation and operation of Softwired Switches and the Softwired Clock and other optional automation devices are located in other sections of this manual and are provided with each hardware unit Before starting read the following installation instructions If you have questions call GE Total Lighting Control Service at 1 877 584 2...

Page 2: ...earance Pulling Wires Route line voltage wiring through the 21 2 knockouts in either the top or bottom of the tub Route Class 2 low voltage dataline from the remote switches or other controls through the 3 4 knockouts in either end Install Interior Power Supply Attach the power supply to the frame bottom of 12 relay interior and left side of 24 or 48 relay interiors and plug the low voltage connec...

Page 3: ... may be softwired to relays within the panel Channels are used to group relays for common control When a ProSys system includes an automation module RCLK8PS Softwired Clock we strongly recommend you turn to the installation instructions for that automation module and complete the documentation before softwiring any relays to channels However if automation is to be provided by an interface to anoth...

Page 4: ... panel address is set higher than 30 the channel LEDs in the panel will flash Setting the panel address to 30 or below will return the panel to normal operation If a panel is set to the same address as another panel then the two panels will not operate properly The ProSys LM panels can be setup in groups of 30 where the panels in a group can be numbered from 00 to 30 Note To ensure good communicat...

Page 5: ...uld be tested for continuity and isolation from ground To test for continuity remove the red and black dataline wires at panel 01 and wire nut together short the wires together Go to the last panel in the series and measure the resistance between the red and black terminals It should be less than 3 ohms Return to panel 01 and restore the red and black wires to their associated terminals For shorts...

Page 6: ...6 DEH40212 Installation Instructions GE Total Lighting Control 41 Woodford Avenue Plainville CT 06062 2000 General Electric Company GE Total Lighting Control DEH40212 BL 0700 R02 ...

Reviews: