Technical Manual
KVCG202/EN M/H11
KVGC202
9.1.7
Test block
If the MMLG test block is provided, the connections should be checked to the scheme
diagram, particularly that the supply connections are to the live side of the test block
(coloured orange) and with the terminals allocated odd numbers (1, 3, 5, 7 etc.). The
auxiliary supply is normally routed via terminals 13 (+) and 15 (–), but check against the
schematic diagram for the installation.
9.1.8
Insulation
Insulation tests only need to be done when required.
Isolate all wiring from the earth and test the insulation with an electronic or brushless
insulation tester at a dc voltage not exceeding 1000V. Terminals of the same circuits
should be temporarily strapped together.
The main groups on the relays are given below but they may be modified by external
connection as can be determined from the scheme diagram.
a) Current transformer circuits.
b) Voltage transformer circuits.
c) Auxiliary voltage supply.
d) Field voltage output and opto-isolated control inputs.
e) Relay contacts.
f) Communication port.
g) Case earth.
Note:
Do not apply an insulation test between the auxiliary supply and
the capacitor discharge terminals because they are part of the
same circuit and internally connected.
9.2
Commissioning test notes
9.2.1
Equipment required
For KVGC202 relays the following equipment is required:
AC auxiliary supply suitable to supply a 30VA load. Frequency of 50/60Hz.
Multi-finger test plug type MMLB01 for use with test block type MMLG.
Continuity tester.
Three phase voltage supply 440V.
440/110V star/star phase shifting transformer AC voltmeter 0 – 440V
DC voltmeter 0 – 250V
AC Voltmeter 0 to 440V range
AC multi-range ammeter
Suitable non-inductive potentiometer to adjust polarising voltage level.
Interval timer
Phase angle meter or transducer. If necessary suitable current shunt(s) for use with the
phase angle meter.
A portable PC, with suitable software and a KITZ101 K-Bus/IEC 60870-5 interface unit
will be useful but in no way essential to commissioning.
Summary of Contents for KVGC 202
Page 2: ......
Page 10: ...KVCG202 EN M H11 Technical Manual KVGC202 ...
Page 122: ...KVCG202 EN M H11 Technical Manual KVGC202 Figure 36 Test circuit diagram ...
Page 123: ...Technical Manual KVCG202 EN M H11 KVGC202 APPENDIX 1 ...
Page 124: ...KVCG202 EN M H11 Technical Manual KVGC202 ...
Page 125: ...Technical Manual KVCG202 EN M H11 KVGC202 Figure 37 Relay inverse time characteristic curve ...
Page 126: ...KVCG202 EN M H11 Technical Manual KVGC202 ...
Page 127: ...Technical Manual KVCG202 EN M H11 KVGC202 APPENDIX 2 ...
Page 128: ...KVCG202 EN M H11 Technical Manual KVGC202 ...
Page 129: ...Technical Manual KVCG202 EN M H11 KVGC202 ...
Page 130: ...KVCG202 EN M H11 Technical Manual KVGC202 ...
Page 131: ...Technical Manual KVCG202 EN M H11 KVGC202 APPENDIX 3 ...
Page 132: ...KVCG202 EN M H11 Technical Manual KVGC202 ...
Page 133: ...Technical Manual KVCG202 EN M H11 KVGC202 W02474 10 KVGC202 00 SHEET 1 ...
Page 134: ...KVCG202 EN M H11 Technical Manual KVGC202 W02475 10 KVGC202 00 SHEET 2 ...
Page 135: ...Technical Manual KVCG202 EN M H11 KVGC202 W02476 10 KVGC202 00 SHEET 3 ...
Page 136: ...KVCG202 EN M H11 Technical Manual KVGC202 W02477 10 KVGC202 00 SHEET 4 ...
Page 137: ...Technical Manual KVCG202 EN M H11 KVGC202 W02478 10 KVGC202 00 SHEET 5 ...
Page 138: ...KVCG202 EN M H11 Technical Manual KVGC202 W02479 10 KVGC202 01 SHEET 1 ...
Page 139: ...Technical Manual KVCG202 EN M H11 KVGC202 W02480 10 KVGC202 01 SHEET 2 ...
Page 140: ...KVCG202 EN M H11 Technical Manual KVGC202 W02481 10 KVGC202 01 SHEET 3 ...
Page 141: ...Technical Manual KVCG202 EN M H11 KVGC202 W02482 10 KVGC202 01 SHEET 4 ...
Page 142: ...KVCG202 EN M H11 Technical Manual KVGC202 W02483 10 KVGC202 01 SHEET 5 ...
Page 143: ...Technical Manual KVCG202 EN M H11 KVGC202 APPENDIX 4 ...