6. SOFTWARE UPGRADE
6. SERVER OPERATION NOTES
6.1. Important Notes
Each time, server boot will take up to five (5) minutes.
In the event of power loss or forced shutdown, server boot may take up to twenty (20)
minutes. The server must complete bootup before playback can be started. It is
recommended to ALWAYS follow proper power up & shutdown procedures (see
section 6.2.).
The SMS will be locked by default.
Ethernet Connection between the Server, SM and Projector is REQUIRED for
successful playback. Customers must ensure the cable is secure and the switch used
(in case of non-IMB systems) is reliable.
6.2. Power Up & Shutdown
This section lists the proper power up and shutdown steps that will result in the most
optimal performance for the servers.
6.2.1. Power Up
a) Power up the projector first and then the server. This is necessary for IMB board
servers to operate properly.
b) It is recommended to reboot the projector if it has been idle longer than 3 minutes
without the connected server powered on.
6.2.2. Shutdown
a) Always shutdown the servers before the projector. This is a
MUST
for IMB servers.
b) Always use the shutdown option from the server interface. Do not unplug the power,
switch off the power switches, or hold down the power button during normal use.