136
www.gateway.com
Chapter 4: Installing Components
8
Plug the power cord into the AC connector on the power supply module.
9
If your server only has a single power supply module, turn on the server.
10
The new power supply module is ready if the green Power Good LED (top) and green
AC OK LED are both on.
Replacing a power distribution board
Your server uses a power distribution board to enable the hot-swap capability and distribute
power to the system. If the power distribution board fails, you will need to turn off the
server and disconnect all AC power to the system prior to replacing it.
To replace a power distribution board:
1
Follow the instructions in
“Preventing static electricity discharge” on page 65
2
Follow the instructions in
“Opening the server case” on page 66
.
3
Remove the power supply module (remove both if two are installed) by following the
instructions in
“Replacing a power supply module” on page 134
.
4
Remove the processor air baffle by following the instructions in
installing the processor air baffle” on page 67
5
Remove the system board by following the instructions in
6
Remove the SCSI backplane by following the instructions in
hot-swap backplane” on page 139
7
Disconnect all power cables from the power distribution board, noting their locations
and orientation. (You will reconnect the cables after you install the new board.)
8510702.book Page 136 Thursday, July 7, 2005 11:21 AM
Summary of Contents for 9715
Page 249: ...244 www gateway com Appendix B 8510702 book Page 244 Thursday July 7 2005 11 21 AM ...
Page 259: ...254 www gateway com Appendix D 8510702 book Page 254 Thursday July 7 2005 11 21 AM ...
Page 277: ...272 www gateway com 8510702 book Page 272 Thursday July 7 2005 11 21 AM ...
Page 278: ...MAN 9715 SRV USR GDE R0 06 05 ...