4.6
START-UP
4.6.1 GENERAL RECOMMENDATIONS
Before proceeding with the commissioning of the equipment is important to always:
1) Check that the equipment is properly installed according to the recommendations set out in item 4.3 of this
manual.
2) Close the input block valves, output and bypass (if applicable) of the leg.
3) Open the vent valve downstream of the last pressure regulator installed on leg.
4) Make sure that the depressurized this station.
5) Make sure all connectors are properly secured the station before proceeding with the pressurization of the
line.
6) Check that the installed equipment is suitable operating conditions through the information available on the
nameplate attached to the equipment.
7) Make sure the SSV is in the closed position.
ATTENTION:
* Under no circumstances do with the line pressurization where the
equipment is installed by the posterior valve equipment.
* Under any circumstances perform depressurization line where
equipment is installed by the valve located at the entrance of the
equipment, such as filters drain.
ATTENTION:
The SSV GASCAT are sent to the already calibrated field, however due
to the conditions of carriage and operation of any equipment the valve
may have its set-point change.
Therefore we recommend that you checked the set-point of the SSV
with the help of a connected external air supply directly to the actuator,
before proceeding with the pressurization of the line.
The model HORUS valves are not sent to field set on their set-point, this
measure tends to preserve the life of the product's internal therefore to
receive a control valve HORUS model pressure, keep in mind that you
need to perform the adjustment set-point before putting the equipment
into operation.
The setting of the pressure reducing station should be in accordance with DIN EN 12186 / NBR 12712 and
all other applicable regulations in the region where it will operate.