Varsity Jam Adjustable Basketball System
10
INSTALL POST
1.
Concrete should be cured for 72 hours before removing
forms and continuing installation.
2.
Place (4) 5/8” Flat washer on top of the (4) 5/8-11 Nuts
as shown in Fig #5.
Fig #5
3.
Raise and place the main post over the J-
bolts as shown in fig #6. The post is heavy,
so use at least two people for this operation.
Be sure that the post is installed with the
Actuator Anchor on the side away from the
court.
4.
Secure post with (4) 5/8” Flat Washer, 5/8”
Lock Washer, and 5/8-11 Hex Nut as shown
in fig 7.
Fig #7 Fig #6
5.
If the post is not exactly vertical, adjust the bottom nuts on the base to level. If the post is
not exactly square to the court, rotate it.
6.
When the post is vertical and square to the court, tighten all nuts securely.