5.0 Installation Procedure
TABLE 3
GAMMA INSTALLATION PROCEDURE
1 Once the positions of the Gamma Bracing Frames (GBF’s) have been determined from the bracing design remove any cross
noggins/dwangs where the GBF’s are to be installed. Ensure the inside dimension of the framing provides a suitable fit for the
GBF’s. A tolerance of +2.0mm and – 0.0mm between the GBF and the timber framing is acceptable. The GBF’s s need to fit snuggly
into the framing.
2 For wall heights of 2.7m and 3.0m install the required timber framing members as detailed.
3
Concrete Floors – External & Internal Walls
Where GBF’s are located in external walls position the GBF’s flush with the inside face of the timber framing to ensure the hold
down fastener is away from the edge of the concrete slab (minimum edge distance = 60mm). For internal walls the GBF’s can be
positioned centrally within the framing.
Timber Floors – External & Internal Walls
Where GBF’s are located in external walls and internal walls the GBF’s can be positioned anywhere within the framing ensuring
the position of the hold down bolt is secured in to solid timber framing.
Once the GBF’s are positioned mark the positions for the hold down fasteners through the slot in the hold down bracket and on
to the bottom plate. Remove the GBF or where possible swing the GBF to one side to allow access for drilling the holes for the
hold down fasteners. To swing the GBF to one side it is useful to install a single Tek screw fastener into each stud (do not fully
tighten these until the GBF is fully installed). Drill the holes for the hold down fasteners.
4
Concrete Floors – Hold Down Anchors
Use M12 x 150mm masonry fasteners or M10 x 140mm Masonry Screw in Anchors (Refer Section 16.2 for recommended types of
anchor).
Timber Floors – Hold Down Anchors
Use M12 x 200mm galvanized coach screw to be fastened into solid timber framing (Refer Section 16.2 for recommended types
of anchor).
5 Reposition the GBF in between the studs ensuring that the slotted holes in the brackets are aligned with holes in the bottom
plate.
6 Install the slotted washer provided and install the hold down anchor and tighten.
7 Each of the hold-down brackets are secured to the GBF framing to allow for shipping and have been pre drilled with 8 holes.
Using the 12g x 40mm Tek screws fasten each bracket to the timber framing (8 screws per bracket).
It is permitted to adjust the brackets up to no greater than 50.0mm and down by no greater than 39mm to allow for any small
deviation in wall framing height. (Refer section 15.8 for further details on height adjustment).
8 Using 12g x 40mm Tek screws provided fix through the pre punched holes located in the GBF’s and into the timber framing.
9 If thermal insulation is to be installed then cut the thermal insulation to fit within the timber framing and Gamma framing
members and ensure that insulation protrudes from both sides of the Gamma Bracing Frame (Refer Section 16.3).
10 If interior sheet linings are to be installed fix as per the manufactures instructions or as per AS/NZS 2589:2017. Minimum drywall
fixing centres to be no greater than 300mm.
Detailed within Table 3 is the procedure for installing the Gamma Bracing Frames (GBF’s). The installation procedure is
designed for onsite installations however the GBF’s can also be installed at the pre nail framing stage of the construction.
Should the GBF’s be installed at the pre stage the GBF’s will have temporary fasteners installed to hold them in place for
the purpose of transportation to the job site. Completion of the installation of the GBF’s must be carried out once the pre
nail framing has been erected using the same procedures as detailed within Table 3.
Summary of Contents for GBF220
Page 42: ...TM GAMMA TM 42 P R O O F 15 3 Construction Details Multiple GBF Frames...
Page 43: ...TM GAMMA TM 43 P R O O F 15 4 Construction Details Concrete Floors...
Page 44: ...TM GAMMA TM 44 P R O O F 15 5 Construction Details Concrete Floors...
Page 45: ...TM GAMMA TM 45 P R O O F 15 6 Construction Details Timber Floors...
Page 46: ...TM GAMMA TM 46 P R O O F 15 7 Construction Details Timber Floors...
Page 50: ...TM GAMMA TM 50 P R O O F Notes...
Page 51: ...TM GAMMA TM 51 P R O O F Notes...