U41644-J-Z816-5-76
A-5
Laufende K/F 1
Figure A.3 Securing a rack with leveling feet
(2)
Cable route inside the rack
The PRIMEQUEST 520A*/520/420 is equipped with a cable management system as
standard equipment designed for mounting in a Fujitsu 19-inch global rack. By
controlling cable slack with the cable management system, the PRIMEQUEST
520A*/520/420 unit can easily be pulled out from the rack while cables remain
connected.
Cables as long as about two meters (6.6 ft.) are required for use of the cable
management system. Consider this length when determining the length of each
interface cable.
*: not supported by Fujitsu Technology Solutions
Front
Leveling foot
Height of floor
250 to 400 mm
(10 to 16 in.)
Bolt (M20)
(Floorboard)
Frame
Anchor bolt
Supporting column