![Fuji Electric FCX-AII-V5 series Instructions Manual And Service Instructions Download Page 24](http://html1.mh-extra.com/html/fuji-electric/fcx-aii-v5-series/fcx-aii-v5-series_instructions-manual-and-service-instructions_2341970024.webp)
22
TN5FCXA2V5h-E
(2) Steam measurement
A condensate chamber must be mounted between
transmitter and process connection.
Fill the pipe between the condensate chamber and the
transmimitter with water.
The installation of a drain is necessary.
Impulse pipe
Manual valve
Pressure source
Stop valve
Recommandation for process connection
(1) Liquid measurement
Place the transmitter below the the process
pipe.
Make piping so that gas in the impulse pipe is
not delivered to the transmitter, and incorporate
gas reservoirs as required.
3.2.3 Absolute pressure (FKH) and gauge pressure transmitters (FKP)
Remove the protective cap
7KH SURFHVV FRQQHFWLRQ SRUW RI WKH WUDQVPLWWHU LV ¿WWHG ZLWK D
protective cap. Before piping, be sure to remove the cap. When
removing the cap, carefully protect the threaded portion and seal-
ing face from damage.
Connect the transmitter to impulse pipes
The piping can be connected directly to the process connection of the transmitter or via an
RYDOÀDQJH,IDQLVRODWLQJYDOYHLVXVHGOHWLWFORVHXQWLOFRPPLVVLRQLQJWRSUHYHQWIRUHLJQ
objects from entering.
For an absolute pressure measurement, make sure that isolating valves or manifold can
be designed for vaccum service.
Position of process connection
The position of the process connection is determined by the relationship between condition,
FKDUDFWHULVWLFVDQGPHDVXUHPHQWSRLQWRISURFHVVÀXLG
Follow the process position according to the process :
Gas measurement
Liquid measurement
Steam measurement
Upper
Lower
Upper
Lower
0 to 45° up from the vertical
0 to 45° up from the vertical
0 to 45° down from the vertical
Impulse pipe
Vent valve
Process pipe
Isolating valve
Pressure tap
4HREADEDPORTION
3EALSURFACE