5
Initial start-up
Perform initial start-up only after all work as described in
‘Installation’ on page 18 has been carried out.
5.1 Switching on
n
The device must be connected to the power supply if this has not
been done already.
n
Switch on the device with the main switch on the back of the device.
n
The POWER lamp on the control panel lights up.
n
The display shows the default setting.
5.2 Function check
n
Fill the mortar (2) with 5 - 10 ml of sand, insert the grinding ball and
clamp the lid (1).
n
Set the amplitude to 2 mm (See
Chapter 6.3 ‘Setting the ampli‐
n
When everything is correctly clamped, start the function check with
"START".
Whether the set amplitude has been reached can be
checked on the display or on the amplitude plate on the lid.
5.3 Switching off
n
Press the STOP key and switch off the main switch.
Initial start-up
- 21 -
Summary of Contents for PULVERISETTE 0
Page 6: ...13 Exclusion of liability 46 14 Safety logbook 48 15 Index 50 Table of contents 6 ...
Page 40: ...NOTICE The plexiglas lid must not be cleaned with alcohol or organic solvents Cleaning 40 ...
Page 48: ...14 Safety logbook Date Maintenance Repair Name Signature Safety logbook 48 ...
Page 49: ...Date Maintenance Repair Name Signature Safety logbook 49 ...
Page 51: ......