Lower down the product slowly.
•
The position control must be maintained with a water gauge on the product. The dry
cooler must be positioned parallel to the surface.
•
Fix the product to the surface.
For the vertical (V) type mounting:
•
Fix the product with 2 lifting eyes and afterwards begin foot mounting.
•
Use 2 spangles and a nut for each bolt must be used.
•
Lower down the product slowly.
•
The position control must be maintained with a water gauge placed on the product. The
product must be positioned parallel to the surface.
•
Fix the product to the surface.
7.
OPERATION
7.1 Initial commissioning
Before running the unit for the first time, be sure that all guards, motor mountings and
electrical covers are secure, installation and electrical connection are done properly, internal
wiring is kept away from the fans and the fans can rotate freely.
Make sure that all the mechanical connections are done in accordance with the rules. Piping is
consistent with the guidelines. Before the start-up you may run the fans individually to make
sure that they are running properly. Turn on the fluid valves and let the fluid flow right before
running the fans. In case you may encounter any problem or disfunction please refer to the
manufacturer for the resolution of the problem.
7.2 Regular commissioning
If the product is stationary for long periods in a humid atmosphere, the fans must be switched
ON for
minimum of four hours in every month
to remove any moisture that may have
condensed within the motors.
While the fans are running, anything that could pass through the finger guards, like a piece of
cloth or long hair, must be kept away from the fans.
•
Switch on the main power switch
•