NOTICE
Failure to comply with these requirements will render any written or implied
Johnson Controls warranty null and void.
Form 210.100-SB2 (MAR 2016)
SERVICE BULLETIN
File:
SERVICE MANUAL - Section 210
Replaces:
NOTHING
Dist:
3, 3a, 3b, 3c
Revised:
May 2017 (Logo)
Long Term Storage Requirements
Field Preparation of Air Handling Units
II. FIELD PREPARATION FOR LONG TERM STORAGE
General
1. Remove and dispose of shipping materials.
2. Perform a visual inspection of the equipment.
Outdoor Units
Outdoor units are not fully wrapped. Exposed openings
are covered for protection from weather, road dirt, etc.
during inland transit. A thorough inspection, both inside
and out, should be done at the time of delivery.
Visible damage should be noted on the signed and dated
bill of lading with a request that the carrier inspect the
damage within 72 hours of notification. Concealed damage
must be reported within 15 days of delivery with a request
that the carrier inspect the damage within 72 hours of
notification. Any concealed damaged reported after 15
days will compromise a claim settlement.
Inspection requests may be done by telephone or in person,
but should be confirmed in writing. If assistance is needed
with the claim process, contact your JCI Sales person.
3. Touch up any paint that has worn or chipped off using
paint supplied in ship loose items. Prepare the surface as
required using a wire brush.
4. Verify that all ship loose items are present. Note any
missing items on the Periodic Checklist and Log Sheet
(210.100-SB3).
5. Locate unit(s) so that passing traffic will not damage shafts,
coil connections, damper linkages or unit panels.
6. Refrigerant coils must be evacuated and pre-charged with
5 psi holding charge of nitrogen. DO NOT damage or disturb
these coils and connections.
7. Water coils must have all inlet and outlet connections
capped or closed tight to prevent foreign materials and
liquids from gaining entrance during the storage period.
I. SUPPLEMENTARY DOCUMENTATION
The following documentation is required to FULLY COMPLY with the Long-Term Storage requirements.
A. Long-Term Storage Requirements – GENERAL (Refer to Form 210.100-SB)
B. Long-Term Storage Requirements – PERIODIC CHECKLIST AND LOGS - AIR HANDLING UNITS (Refer to Form 210.100-SB3).
Upon completion of the long-term storage period, the standard AcuAir warranty commences.
12 MONTHS PARTS ONLY (Not to exceed 18 months from ship date.)