INSTALLATION INSTRUCTIONS
UNPACK CARTONS
Remove the wood board structure and plastic wrap around the unit. Remove the two (2) boxes (carton
assembly and set up gauge box) , and the boom assembly and place aside.
If any problems occur, refer to the shipping and receiving instruction that were attached to the front of the
machine. Double check the cartons for any miscellaneous items or other manuals before disposing of cartons.
REMOVE GRINDER FROM WOOD PALLET
To remove the grinder base from the wood pallet, unbolt the four bracket that hold the frame to the wood
pallet. Use a fork lift to lift the machine from the pallet in the location indicated on the machine.
The unit weighs 817 LBS. [371 kg], use
power equipment to lift the unit.
UNSTRAP CARRIAGE AND INSTALL BOOM
After the machine is in position Remove the shipping strap
which holds the carriage in place. install the boom assembly
into the support on the side of the machine. See Figure 6.
OPERATOR'S AREA
RESTRICTED AREA
PLACING THE GRINDER ON
FLOORING THAT IS BADLY OUT OF
LEVEL OR BROKEN WILL AFFECT
GRINDING QUALITY.
Access to the rear of the machine is only allowed when all switches are in the
OFF
position, the
Emergency Stop Button has been pressed, and all movement has come to a complete stop on the
machine.
ENTERING THIS RESTRICTED AREA WHILE THE MACHINE IS RUNNING IS PROHIBITED
.
Appropriate measures should be taken to mark the floor as a restricted area and barriers should be
installed if neccessary to restrict access to this area. ONLY TRAINED OPERATORS should be allowed to
access this restricted area. Operators must stand in the area marked "OPERATORS" area on Figure 5 when
running this equipment. The equipment should never be left unattended when running.
I
t is recommended that this machine is installed in a separate area of the facility, such as a dedicated grinding room
where access to the equipment can be restricted and proper ventilation can be provided.
FIG. 5
FIG. 6
POSITION BASE
This machine must be positioned in an area that allows for
sufficient access to all sides of the machine for operation
and service. It is suggested to have an operating area of
about 138" [351 cm] x 114"D [290cm] x 90"H [229 cm].
Position the base to allow sufficient operating room in both
front (Operators Postion) and behind (Reel Loading Postion)
the machine. See Figure 5.
The base should be placed on a relatively level concrete
floor, with ample ceiling height to allow for the installation
and operation of the reel winch and boom. Do not place
the unit across two concrete slab seams or across a large
crack.