Apply mains voltage to level switch NRS 7.
Commissioning
Check that the NRS 7 and the associated level electrode are wired in accordance with the wiring
diagram,
Fig. 10, Fig. 11
.
Checking wiring
Apply mains voltage
Performance test
. Check length of electrode rod (see installation manual of the level electrode).
. When switching on the mains voltage the green LED
"
should be permanently illuminated,
Fig. 7
.
. Completely open valves of waterlevel gauge glass on steam boiler.
4. Fill boiler with feedwater ( cm above required level).
5. Decrease level in boiler until the level falls below low level. After the response delay has elapsed
the two red LEDs
0
on the level switch must light up.
If the automatic selfchecking test is initiated during this phase an alarm will only be raised after
twice the nominal delay period.
6. A lowlevel alarm can be simulated by pushing the button “TEST ”
!
with the electrode tip
submerged. Push the button until the response delay has elapsed. Both red LEDs
0
must light up.
7. The checking circuitry of the level switch can also be checked. Operate switch “TEST /Inspection”
9
in the direction of the arrow with the electrode tip submerged. After max. two minutes the two
red LEDs
0
should signal lowlevel alarm. The button “TEST ”
!
must
not
be operated during
this test
nor
must the level fall below the low level mark.
After the test return switch
9
into its original position. After the response delay the two red LEDs
0
must extinguish.
Lowlevel limiter
EN
EN
Summary of Contents for NRS 1-7
Page 2: ... ...
Page 3: ... Deutsch Seite 4 21 English Page 22 39 DE EN ...
Page 10: ...10 Technische Daten Fortsetzung Maße Fig 2 106 7 32 51 Fig 3 112 85 DE ...
Page 11: ...11 Aufbau Fig 6 7 2 3 6 5 4 Fig 4 Fig 5 1 1 NRS 1 7 DE ...
Page 12: ...12 Funktionselemente NRS 1 7 Fig 7 9 0 MAX 55 C MAX 95 IP 65 DE ...
Page 15: ...15 Einbau Fortsetzung Einbaubeispiele 4 2 5 8 6 6 3 1 Fig 9 Fig 8 7 7 DE ...
Page 28: ...28 Technical Data continued Dimensions Fig 2 106 7 32 51 Fig 3 112 85 EN ...
Page 29: ...29 Design NRS 1 7 Fig 6 7 2 3 6 5 4 Fig 4 Fig 5 1 1 EN ...
Page 30: ...30 Functional Elements NRS 1 7 Fig 7 9 0 MAX 55 C MAX 95 IP 65 EN ...
Page 33: ...33 4 2 5 8 6 6 3 1 Installation continued Fig 9 Fig 8 Examples of Installation 7 7 EN ...