8
Step 4: Install flue, In-line Fan, Air supply duct bracket, Air supply
duct and connect to appliance
Flue installation must meet the requirements of AS/NZS 5601.1:2013 must comply with all local
council requirements and be installed and certified by a suitably qualified person.
Refer to appropriate Fire Dept product specification for specific minimum requirements. Only follow the
‘
Wall
cowl assembly details
‘ (below) if the flue is required to terminate through the wall.
A 25mm clearance from combustible materials, 75mm clearance from wiring and plastic pipes and a
minimum of 5mm from non-combustible materials is required when installing a flue system for any fire
supplied by The Fire Dept.
The flue installation requires a restriction free cavity from the top of the firebox (flue spigot) to the outside
atmosphere.
Follow the
In-Line Fan assembly details
below.
Air flow must be unobstructed from the firebox to the inner flue and from the heat shield to outer casing
allowing air to circulate from the firebox to the flue casings to the atmosphere.
Connect the
Air supply duct bracket
to the flue / wall spigot at the flue penetration to termination.
Run the
100mm Aluminium Semi-Rigid Ducting
from the
Air supply duct bracket
to the
100mm air
supply spigot
on the top of the fire box. Refer to appropriate Fire Dept product specification for specific
fixing requirements.
The
100mm Aluminium Semi-Rigid Ducting
will require a joint if the flue run is over 6 meters. Refer to