13
Revision date: 09.21.18
113542
Plumb and Level Each Frame Pod
5
3. At the end walls, adjust the levelers to level the frame side-to-side. Set a level on the end frame cross member and adjust. See diagram C.
PLUMB AND LEVEL EACH FRAME POD—continued
4. Repeat Step 2 to recheck the back-to-front slope.
5. Verify that all levelers are locked in place.
For improved stability, avoid fully extending the levelers.
6. Assemble and set the next pod in position and repeat this procedure (Procedure 5).
7. After assembling pod frames, set in place, leveled, and plumbed, install the 112770 finishing plug in the top of each vertical frame tube.
8. Continue with the installation of the gutters and downspout.
DIAGRAM C
Lock Nut
STEP 3
Install one 112770 finishing cap in the top of each vertical
frame tube. Gently tap into tube if needed.
112770