3. Packing, transport and storage
Only skilled personnel who are familiar with the lift and this manual shall be allowed
to carry out packing, lifting, handling, transport and unpacking operations.
3.1 Packing
The packing of the lift is delivered in following components:
Base unit packed in a steel frame, wrapped up in non-scratch material, including the all
accessories.
Power unit packed in a carton box.
Electric panel packed in a carton box
(If requested, optional accessories are available to satisfy each customer’s requirements).
3.2 Lifting and handling
When loading/unloading or transporting the equipment to the site, be sure to use suitable loading
(e.g. cranes, trucks) and hoisting means. Be sure also to hoist and transport the components
securely so that they cannot drop, taking into consideration the package’s size, weight and
centre of gravity and it’s fragile parts.
3.3 Storage and stacking of packages
Packages must be stored in a covered place, out of direct sunlight and in low humidity, at a
temperature between -10°C and +40°C.
3.4 Delivery and check of packages
When the lift is delivered, check for possible damages due to transport and storage; verify that
what is specified in the manufacturer’s confirmation of order is included. In case of damage in
transit, the customer must immediately inform the carrier of the problem.
Packages must be opened paying attention not to cause damage to people (keep a safe
distance when opening straps) and parts of the lift (be careful the objects do not drop from the
package when opening).
4 Installation
Only skilled technicians must be allowed to carry out installation. Serious damage to
people or lift can be caused by incorrect installations.
4.1 Space required
The lift must be installed on a level concrete floor, having minimum thickness of 20cm and an
extension of at least 1.5m from anchoring points.
The lift installation concrete surface must be perfectly smooth.