2.5 INSERTING THE BOLLARD IN THE PIT
To place the bollard in the previously prepared pit (wait at least 7 days
for the cement to set), you must screw two eyebolts M20 on the top
part, as shown in the figure below, using them as hooking points for
the lifting operation with belts or chains.
Before inserting the bollard in the pit, wire as described in the
previous chapter and check its correct operation, also checking the
correct intervention of the safety devices (see "JE275 ELECTRONIC
EQUIPMENT" on page 11).
Lift and insert completely the bollard in the pit.
During this phase ensure the cable is positioned correctly to prevent
it from being crushed between the pit and the bollard frame.
After completely inserting the bollard and resting it on the pit
counter-frame, remove the two eyebolts and secure the bollard to
the pit using the 15 provided cylindrical head screws with hexagon
socket M20x45.
IMPORTANT:
TIGHTEN THE 15 SCREWS USING
200Nm
TORQUE
2.6 FASTENING THE TOP CROWN
After having secured the bollard, complete the installation positioning
and securing the top crown with 8 cylindrical head screws with
hexagon socket M8x30 INOX supplied standard
Cable length out of
pit: 2.5m