DT200-EU-EN-V2.0 4/12
7
Indirect Measurements
(Using Three Measurements)
The DT200 can measure height in two segments by taking three measurements. The operator
stands at Point X. The first measurement is Point X to 1, the second measurement is a horizontal
line from Point X to 2, and the third measurement is from Point X to 3.
1.
Press the MEAS button to switch the meter ON. Wait several seconds and the Laser pointer
will switch ON.
2. Press
the
button two times.
3.
The triangle icon
will appear with its bottom diagonal line flashing.
4.
From Point X aim the instrument at Point 1 and press MEAS. One reading is now complete
and the middle line of the triangle will begin flashing.
5.
Press MEAS again to turn on the laser pointer to prepare for the next measurement.
6.
From Point X, aim the instrument horizontally at a Point 2 and press MEAS. The second
reading is now complete and the top diagonal line of the triangle will begin flashing.
7.
Press MEAS to turn on the laser pointer and prepare for the third measurement.
8.
From Point X, aim the instrument at Point 3 and press MEAS. The third measurement is now
complete.
9.
The distance from Point 1 to Point 3 will now be indicated on the bottom display line.
X
1
2
3