11.5.2 Cooldown timer
When the switch returns in position I the Cooldown timer will start counting (Default value 180s) during the cooldown timer, the
contacts will maintain the generator start signals.
11.5.3 Dead band timer ODT
The dead band timer ODT can be configured using the DIP switches 5 (2s or 0s). This timer defines the time for which the switch
should stay in the 0 position when transferring from one source to another.
11.6
Priority settings
Priority settings ca
n be configured using the DIP switch 2 “PRIO SET” or through
communication. The priority can be set to:
11.6.1 S1, in this case when source 1 is available the controller will give the order to switch to position I
11.6.2 No prio, if both sources are available the controller will give the order to remain in the current position.
12 Tests
The C25 allows for 2 test functions using the HMI test button:
A short press on this button (<3s) will start a LED test, allowing the user to check that all LEDs are functional.
A long press (>3s) on this button will start a TEST ON LOAD, this test will start the genset, and transfer to the Source II once the
source is considered available.
The product will remain on source 2 until the test ends, to end the test press again the test button for more than 3s to return in
the last working mode (Manual or Automatic).
It is also possible to start and stop the test on load and off load through communication
Summary of Contents for 004661922
Page 1: ...EN INSTRUCTION MANUAL ATSC25 ATS Controller www eti eu support...
Page 25: ...EN 25 11 2 Connection diagrams 11 2 1Connections with MLBS 4P 63 125...
Page 26: ...26 EN 11 2 2Connections with standard Contactors CEM and CES...
Page 27: ...EN 27 11 2 3Connections with MCCBs EB2 and MO2...
Page 34: ......