ESWOOD OPERATING MANUAL ES-32 June 2011
7
I
NSTALLATION
4
1.
Remove the packing materials from the machine, including
inside the chamber.
2.
The machine is supplied ready for straight-through operation. If
corner use is required remove the three screws holding the front
rack track guide and bolt to the right hand side of the rack track.
3.
Remove the lower panel, position the machine and level by
screwing the adjustable feet.
4.
Fit the line strainer supplied to the water supply.
5.
Connect the 2” B.S.P. gravity drain via a 2” trap to the drain
outlet.
Note that all plumbing work is to be done in accordance with
local plumbing codes.
6.
Connect the hot water inlet to a ½” B.S.P.isolating valve
adjacent to the machine. The hot water input supply should be
between 100 to 400 kPa and a minimum of 65
°
C. A pressure
reducing valve should be fitted for pressure above 400 kPa.
.7.
Ensure the Rotary switch on the control panel is in the ‘OFF’
position then open the control panel and connect the 3-phase
power to L1, L2 and L3. Then connect neutral to “N” on the
terminal block and connect the earth wire to the earth terminal.
An isolator is also required adjacent to the machine. When
finished, check that the directions of rotation of the wash motors
are in accordance with the arrows on the motor housings.
(Return isolator and rotary switch to ‘OFF”).
Note that all electrical work is to be done in accordance with the
rating plate on the lower panel and local electrical codes.
WARNING
: Check the Rinse Tank is full of water before turning
on the electrical supply as burnt out elements are not covered by
the warranty. To fill tank simply open isolating valve. Tank will fill
with water till level is reached.
8.
Connect the benching so that there is a fall back towards the
machine to allow water to drain back into the machine.