Spraybar DN25 Installation Manual
11
14/06/2021
SECTION 5 - COMMISSIONING
Step 1.
TURN WATER SUPPLY ON
Double check the items in previous sections - safety - preparation -
installation.
Step 2.
TURN ON SUPPLY TO THE SPRAYBAR
If a solenoid valve is used, have electrical personnel override the controls to
open the valve for testing and commissioning, with the conveyor locked out.
Check all joints for leaks. (If there are any leaks, isolate the water supply,
dismantle the appropriate joint and reseal with appropriate thread sealing
tapeor compound).
Step 3.
CHECK SPRAY IMPACT POINT
If the spray impact point is not at the intended position, loosen off the lock
screws and rotate the Spraybar as required.
Once correct spray impact point is achieved, tighten the lock screws.
Check the water spray pattern adjacent patterns are overlapping. If adjacent
spray patterns are colliding, use a spanner to rotate the nozzles slightly to
prevent, until the patterns just clear.
Step 4.
START THE CONVEYOR
Follow the established safety rules.
Step 5.
OBSERVE THE CLEANING ACTION
If installed as part of a total cleaning system with ESS Primary and
Secondary cleaners then observe the cleaning action of the entire system.
Place some product on the belt and look to see that all cleaners are
operating properly.
Step 6.
DEMONSTRATE THE SYSTEM TO THE OPERATING SUPERVISORS
AND CREW
Call the supervisors responsible for maintenance and operation of the site.
Make a short run of the system, putting material on the belt. Show the
operator how to adjust and operate the system.
Step 7.
SECURE THE SYSTEM FOR PRODUCTION
Follow plant procedure to secure the conveyor for actual production.