630184_4 IB Installation Manual NZ
18
13.0
Masonry Cavity and Chimney:
The heater can be flued with 100mm flexible aluminum ducting in accordance with
AS/NZS5601. This single skinned flue must only be used where the path of the duct never
comes into contact with combustible materials.
13.1 The top of the flue must be capped with an appropriate anti down draft cowl.
Note:
Chimney liner flue kits intended for other brands of heater may not fit. Escea flue
spigot is 100mm inside diameter.
14.0
Laying Gas Pipe:
Gas pipe should be sized as per the requirements of AS/NZS5601. The pipe sizing must be
sufficient to deliver the following volume of gas to the heater with all other gas appliances in
the home running at the same time;
IB1100 = 43MJ/hr
IB850 = 43MJ/hr
IB600 = 36MJ/hr
14.1
Gas connection is via ½” female BSP at the front right of the fire.
14.2 The Zero Clearance Kit has 3 possible entry points for solid gas pipe, on the two rear
corners and the front right. Each is sealed by a „knock-out‟. Remove only the knock-out
which you require, and place the supplied rubber plug into the hole. You will need to make a
small cut into the rubber plug to allow the gas pipe to pass through, keeping the plug as air-
tight as possible.
Install gas lines to
any of these 3 points.
Leave enough piping
to reach the front
right hand corner of
the ZCK once
installed.
Electrical
point of
entry.
Final gas connection point
(after ZCK installation)
Plan view from top looking down.
Gas pipe