background image

8

1.  Before operating this equipment for the first time, 

and periodically thereafter, review the SAFETY 
INFORMATION beginning on page three of  
this manual.

2.  The standard sump cleaner LP gas engine is 

equipped with LIQUID WITHDRAWAL regulators, 
for use with either LIQUID or VAPOR 
WITHDRAWAL LP GAS BOTTLES.

3.  Suction and discharge cycles are controlled by a 

four-way valve in the piping from the SUCTION/
DISCHARGE pump to the tank. Placing the 
valve’s control lever in the horizontal position 
selects the SUCTION mode (FIGURE 1). Moving 
the lever a quarter turn to the vertical position 
selects the DISCHARGE mode (FIGURE 2).

lp Gas Models
Operation

FIGuRE 1 

Suction/Discharge lever - SUCTION position

FIGuRE 2 

Suction/Discharge lever - DISCHARGE position

4.  Place the SUCTION/DISCHARGE lever in the 

horizontal (SUCTION) position. Open the LP Gas 
bottle valve. Open the suction inlet ball valve.  
Place choke in “ON” position (FIGURE 3).  
Turn ignition key to the “START” position  
(FIGURE 4) while moving choke to the “OFF” 
position. Release key when the engine starts  
and move choke to the “OFF” position.

FIGuRE 3 

Pull out for CHOKE

FIGuRE 4 

Turn key to START

5.  Vacuum coolant and chips from the sump.

6.  As soon as fluid stops passing through the hose, 

stop the engine by turning the IGNITION switch 
OFF. Close the gas bottle valve. This valve must 
always be closed when engine is not running.The 
tank’s maximum capacity is, at most, 10% above 
the rated capacity. A float switch in the tank and 
wired into the engine ignition circuit will shut down 
the engine if overfilling starts to occur. If this 
happens, place the IGNITION switch in the OFF 
position, and close the gas bottle valve. Follow 
instructions for the discharge operation in Item 7.

7.  To return filtered chip-free coolant to the 

sump, or wash down the machine, or 

discharge dirty coolant into your recycling  

or disposal system,

 close the suction inlet ball 

valve. Move the four-way valve control lever to  
the vertical (DISCHARGE) position. Open the  
gas bottle valve and place choke in “ON” position. 
Turn ignition key to the “START” position while 
moving choke to the “OFF” position. Release key 
when the engine starts and move choke to the 
“OFF” position. Depress the discharge hose 
nozzle valve. 

Summary of Contents for FJ-310A

Page 1: ...eaner 1 Installation Operation and Maintenance Instructions FJ 310A Sump cleaner ERIEZ MAGNETICS HEADQUARTERS 2200 ASBURY ROAD ERIE PA 16506 1402 U S A WORLD AUTHORITY IN SEPARATION TECHNOLOGIES P C 7...

Page 2: ...E FEATURES 4 SUMP CLEANER WARRANTY 5 ASSEMBLY 6 OPERATING TIPS 7 LP MODELS 8 LP GAS DUAL TANK MODELS OPERATION 10 AIR OPERATED MODELS 11 AIR VENTURI DUAL TANK OPERATION 15 120V MODELS 13 120V DUAL TAN...

Page 3: ...fter operating engine driven units LP gas or gasoline in the discharge mode and before stopping engine turn the SUCTION DISCHARGE lever to the SUCTION position The engine will SPEED UP momentarily and...

Page 4: ...eak proof round cleanout doors are faster and easier to remove and replace than the oval internal manholes used by other manufacturers The thick pliable gasket bonded to the cleanout door virtually el...

Page 5: ...turers for purpose of pursuing warranty claims or making service arrangements or any other purpose Copies of such third party sub assembly manufacturers specific warranty information will be shipped w...

Page 6: ...ake out the following items A Filter basket factory assembled with sleeve B Discharge hose with nozzle C Suction hose D Cleaning tool E Spare filter sleeve or filter bags F LP bottle brackets on LP mo...

Page 7: ...th water soluble coolants and another for use with cutting oils If you must use one unit for both the sump cleaner must be thoroughly cleaned when switching products If at all possible purchase a filt...

Page 8: ...n Release key when the engine starts and move choke to the OFF position Figure 3 Pull out for CHOKE Figure 4 Turn key to START 5 Vacuum coolant and chips from the sump 6 As soon as fluid stops passing...

Page 9: ...of fluid in the bottom of the compartment This is unimportant if the compartment is used for one type of coolant only If different coolants are involved remove the compartment s drain plug to empty it...

Page 10: ...suction and discharge hoses to the proper fittings on that tank compartment Cap off all other fittings 5 For dirty fluid suction operation Activate the Pull out for CHOKE Turn key to START float swit...

Page 11: ...d operation closed discharge open suction Failure to do so will allow particulate to enter the valve seat and seize the valve D As soon as fluid stops passing through the hose release pressure by shif...

Page 12: ...mit switch bypasses the float switch needed to prevent overfilling during the suction operation but is not required for discharge operation The engine won t start in the discharge mode if sump cleaner...

Page 13: ...eded Inspect tank for sludge buildup clean as needed Check blower oil level add SAE 40 non detergent oil as needed Grease blower use 2 bearing grease 500 hours Check engine air filter replace as neede...

Page 14: ...uld be taken out of service immediately until the parts are repaired or replaced DO NOT eliminate the safety release valve or replace it with a release valve rated higher than 15 PSI DO NOT reset the...

Page 15: ...tower during removal position the lifting power source e g crane directly over the center of the basket D Hoist the basket Keep hands and fingers clear If the basket is binding and unable to lift free...

Page 16: ...harge nozzle D Attach the nozzle end of this hose to the clean coolant supply tank Turn on the compressed air and reattach the discharge nozzle to the hose when full Close vacuum valve V2 The compress...

Page 17: ...ON position NOTE THE FLOAT SWITCH WILL ONLY WORK WHEN SUCTION ON IS SELECTED IT IS NOT WIRED INTO THE DISCHARGE ON CIRCUIT 3 Connect the Sump Cleaner to the electrical supply specified on the electri...

Page 18: ...eposition the lifting device so that the basket exits the center of the tower E DO NOT TOUCH BASKET DURING REMOVAL F Position the basket over the waste receptacle G For 50 gallon units empty contents...

Page 19: ...containing the motor assembly C Close valve S 1 D Attach the 1 1 2 hose to the clean coolant compartment inlet port and remove the discharge nozzle F Attach the nozzle end of this hose to the clean c...

Page 20: ...cuit to drop out at a predetermined liquid level in the tank preventing overfilling and pump damage The discharge circuit has no such float switch therefore the sump cleaner must be plugged into outle...

Page 21: ...center of the tower return lower basket to the sump cleaner tower Reposition the lifting device so that the basket exits the center of the tower E DO NOT TOUCH BASKET DURING REMOVAL F Position the bas...

Page 22: ...valve V1 attach the 1 1 2 hose to the discharge port place the discharge nozzle in the machine sump push the DISCHARGE button and depress the discharge hose nozzle valve A Be sure the suction inlet ba...

Page 23: ...ce Schedule 9 To discharge clean fluid to refill a machine sump close the suction inlet ball valve V1 attach the 1 1 2 hose to the discharge port place the discharge nozzle in the machine sump push th...

Page 24: ...of the tank Remove these periodically by opening the drain plug and with the filter basket out of the sump cleaner flush the tank with a water hose 6 Periodically while the basket is out of the tank c...

Page 25: ...Check for obstructions physically remove 2B Check for cracks or holes replace 3 Air leakage 3 Check all hose connections for tightness make sure female quick disconnect fittings have gaskets in place...

Page 26: ...l coolant supplier for corrective action LP Engine Stalls During Discharge or Suction 1 Engine 1 Check engine RPM adjust as necessary 2 Regulator 2 Pressure or vacuum regulator could be out of adjustm...

Page 27: ...Sump Cleaner 27...

Page 28: ...0 345 4946 Fax 814 838 4960 International Fax 814 833 3348 Web Site http www eriez com e mail eriez eriez com Manufacturing Facilities AUSTRALIA BRAZIL CANADA CHINA INDIA JAPAN MEXICO SOUTH AFRICA UNI...

Reviews: