RAK112_ENG / © Ensto 2019
8.
Remove the nuts and washers from the ground mounting box.
9.
Open the distribution cabinet’s maintenance door.
10. Lift the distribution cabinet module on the mounting box and bolt it in place, max. tightening torque
14 Nm.
11. Remove the supply cable sheath at the length of max. 200 mm.
12.
Cut the supply cable conductors to different lengths. Cut the ground conductor longest, so that if a
fault occurs it is the last one that comes loose.
13. Strip the supply cable conductors 25 mm.
14. Connect the supply cable wires to the distribution cabinet power connectors.
15. Ensure strain relief to the cable by fastening the cable with e.g. MUPRO EuroQuick. Select a suitable
strain relief according to the cable diameter.
16. Connect the supply to the charging points using intervening connection cables. The intervening con-
nection cables are pre-connected to the distribution cabinet power connectors.
17.
Pull the intervening connection cables first down through the mounting box hole on the distribution
cabinet side and then up through the mounting box hole on the charging point side.
18. Open the charging point’s maintenance door.
19. Lift the charging point module on the mounting box and bolt it in place, max. tightening torque 14 Nm.
20. Connect the intervening connection cable conductors to the supply terminal blocks located in the
charging points’ maintenance space with max. tightening torque 12 Nm.
21. Ensure that the PE is connected.
22. Switch on F0, F1, F2 (if present) and QF1.
23. Install the second charging point module accordingly.
24. Secure the top cover plate on the charging point and distribution cabinet modules with the washer and
screw included in the delivery.
25. Close the maintenance doors.
Top cover plate
Cable route
Cable entry