       Mount the IQ Battery(ies) on the wall

WARNING

: Risk of injury. Take care when lifting.  

Each IQ Battery base unit is heavy (44.2 kg/ 97 lbs) and re

-

quires two persons to lift.

WARNING! 

Risk of injury and equipment damage. Avoid 

dropping the IQ Battery(ies). Doing so may create a hazard, cause 

serious injury, and/or damage the equipment.

WARNING! 

Risk of injury and equipment damage. Protect the 

IQ Battery(ies) from impact damage and improper use.  

A )  Two person together must lift a single IQ Battery base unit from 

the packaging and place it right side up on a flat surface.

B )  Locate the IQ Battery lifting handles:

C )  If installing multiple battery units, plan to install the IQ Battery 

unit located closest to the main supply. 

D )  The first person lifting must slide the longer front handle under 

the front edge of the IQ Battery, then tilt the handle up so that 

handle tabs engage with the slots on the front side of the 

battery. 

E )  The second person lifting must slide the shorter side handle 

under the left or right side (as needed) of the IQ Battery, and 

support the upper back of the IQ Battery with their free hand.

F )  Together, lift the IQ Battery and bring it to the already mounted 

bracket. 

G )  Hold the IQ Battery at an angle so the top of the unit sets into 

the top of the wall-mount bracket. 

WARNING! 

Risk of injury and equipment damage. Do not 

release the IQ Battery unit until you ensure that the IQ Battery 

unit is fully seated in the wall-mount bracket shelf. 

H )  Once the top of the battery is engaged with the top tabs of the 

wall-mount bracket, keep the battery vertical, make sure the 

battery is flush against the bracket, and lower the battery down 

until fully seated with the wall-mount bracket and set into the 

bracket shelf.

I )  Remove the handles and reserve for the next IQ Battery 

installation.

J )  Use a Phillips screw driver to loosen the screws securing the 

field wiring compartment cover and remove the cover. Keep the 

cover and screws handy as you will need them later.

 K ) Attach the battery to the mounting bracket aligning the screw 

hole at the top of the battery with the screw hole at the top of 

the bracket. 

L )  To record the installation of each IQ Battery base unit, scan 

the serial number label using Enphase Installer App™ and your 

mobile device.

5

Top screw hole

DC Switch

Scannable serial 

 

number label

IQ Battery 

IQ Battery 

IQ Battery front 

handle

IQ Battery side 

handle

       Install conduit and field wiring

DANGER!

 Risk of electric shock. The DC switch must be in the 

Locked position before performing this step.

A )  If not already done, use a Phillips screw driver to loosen the screws securing 

the field wiring compartment cover and remove the cover. Keep the cover and 

screws handy as you will need them later.

B )  Remove the sealing plug for entry into the field wiring compartment. If 

installing only one battery or when installing the last battery in the array, 

seal up the hole with the supplied sealing plug. 

C )  Size the conductors (Lines and Ground) to account for voltage rise and 

to conform to the tables below. Design for a voltage rise total of less than 

2%. IQ Battery can use any circuit breaker size between 10 A and 40 A. 

Breaker rating and wire size are installation dependent. 

Number of 

 

IQ Battery E3/E10 units

Current 

(A)

Minimum wire 

size (AWG)

Breaker 

rating (A)

1*E3

5.3

14

10

2*E3

10.7

14

15

3*E3 or 1*E10

16.0

12

20

4*E3 or (1*E10 + 1*E3)

21.3

10

30

5*E3 or (1*E10 + 2*E3)

27.7

8

35

6*E3 or 2*E10 or 

(1*E10 + 3*E3)

32.0

8

40

       *E3 refers to IQ Battery 3

       *E10 refers to IQ Battery 10

In all cases in the table, it is possible to always use larger conductors and 

a breaker sized for that conductor or smaller. For Example in row 3, with 

3*E3 or 1*E10, it is possible to use:

             a) 12 AWG wire with 20 A breaker, or 

             b) 10 AWG wire with 20 A or 30 A breaker, or

             c)  8 AWG wire with 30, 35, or 40 A breaker

6

Summary of Contents for ENCHARGE-3-1P-NA

Page 1: ...guration for back up of the entire main load panel This configuration supports up to an 80A breaker for the PV circuit and an 80A breaker for battery storage Whole home backup with IQ System Controller as service entrance and PV combiner connected to main load panel This is the preferred configuration when you back up the entire main load panel and the size of the PV combiner circuit is more than ...

Page 2: ...t screwdriver socket wrench torque wrench level wire stripper and stud finder if installing on studs Fasteners for wall mount bracket Slots are 6 8mm 0 27 Check with a structural engineer and local standards for requirements Single wide bracket Three 1 4 lag bolts or screws 7 6 cm 3 inches long depending on attachment wall Triple wide bracket Nine 1 4 lag bolts or screws 7 6 cm 3 inches long depen...

Page 3: ...ction circuit The subpanel could be a small two circuit box with circuit breakers The circuit breakers in the box would have to be suitable for back feeding per NEC 408 36 D Select the right size subpanel and breakers based on the number of IQ Battery units being installed Up to four IQ Battery 10s or twelve IQ Battery 3s can be safely connected to 80A load center To do this you must purchase an o...

Page 4: ... mounting holes on the left and right align with the adjacent studs B Use a level to keep the bottom of the wall mount bracket level C Use 1 4 screws or masonry attachments for masonry to attach the bracket using one screw and washer for each slot 6 8mm 0 27 Use screws in each section of the mounting bracket to support the three IQ Battery units There is an array of slots so that you can choose th...

Page 5: ...J Use a Phillips screw driver to loosen the screws securing the field wiring compartment cover and remove the cover Keep the cover and screws handy as you will need them later K Attach the battery to the mounting bracket aligning the screw hole at the top of the battery with the screw hole at the top of the bracket L To record the installation of each IQ Battery base unit scan the serial number la...

Page 6: ...to its correspond ing conductor Lines and Ground Each terminal accepts two 14 8 AWG conductors 11mm 7 16 inch strip length Tighten to 14 lb in G If installing an IQ Battery 10 route the wires from the first IQ Battery to the adjacent IQ Battery through the inter unit raceway There are two positions for each line and for ground in the terminal block to allow for daisy chaining WARNING Risk of equip...

Page 7: ...crews to attach the cover to the batteries Tighten the screws as needed 8 IQ Battery 10 without cover A Use the Enphase Installer App to commission the IQ Battery ies Once connected to the IQ Gateway refer to the Enphase Installer App help topics for more information B After the IQ Gateway has detected the IQ Battery ies the IQ Battery LEDs operate as described in the following section CONFIGURE a...

Page 8: ... the IQ Battery ies in storage ensure that AC power is not present and that the DC switch is in the Locked position While in storage damage to the battery can occur from over discharge If the battery state of charge falls to 0 the IQ Battery ies can be damaged or destroyed Because of this the IQ Battery ies must only be stored for a limited amount of time The IQ Battery ies must be installed and e...

Reviews: