EnerWorks Solar Water Heating Appliance
© 2011 EnerWorks Inc. - Page
41
-
Energy Kinetics Inc. / Installation
Manual
of perforated, painted, galvanized steel and triangular end caps. Perforations ensure proper
functioning of patented stagnation-control mechanism. Each section of leaf guard is slightly
longer than collector is wide.
1. Insert lower edge of leaf guard section into side-wall groove at top of collector. Align side
edge of leaf guard section with outer side of collector or with side flashing. Leaf guard
sections are overlapped to ensure edges are flush with outer collector side-walls.
2. Secure leaf guard to roof with included roofing screws.
3. Insert triangular caps into left and right leaf guard ends. Secure end caps to roof with
included roofing screws (
Fig.6.3.1
).
4. Secure end caps to leaf guard sections and secure sections to each other at overlaps with
self-drilling screws.
5. Bend center-flashing down to leaf guard and secure with self-drilling screws if applicable
(
Fig.6.3.1
).
Fig. 6.3.1 – Two collectors with center-flashing
and leaf guard.
7 - Appliance Start-Up
1. Install Energy Station cover and secure with supplied screws.
2. Plug in Energy Station. Ensure Energy Station is surge protected. Observe that temperature
differential (
Δ
T) is displayed.
3. Insulate any exposed fittings, heat transfer fluid line or water line. Ensure temperature set
points of solar storage tank, water heater and anti-scald valve are properly set and meet local
codes and regulations.
4. Remove plastic foil cover from collectors.
5. Check Energy Station operation and Controller display to ensure Appliance is working
properly.
Center-flashing folded down and
secured flush with leaf-guard