Commissioning
Proservo NMS83
80
Hauser
9.3.6
Commissioning check
This procedure is to confirm that all calibration steps have been completed appropriately.
1. Navigate to: Diagnostics → Device check → Commissioning check → Commissioning
check
2. Select the
Start
option.
Executing
option is shown on the verify drum table.
3. Select the
Next
option.
4. Confirm that the
Commissioning check
wizard shows the
Finished
option.
5. Confirm that the
Verify drum table
parameter is passed.
This completes the commissioning check procedure.