Enatel DC System Manual
Page 9 of 31
3.4
DC Cabling
CAUTION:
Use extreme care when fitting batteries & their connections. Remove all jewellery
and rings from oneself prior to commencing the installation. Always use insulated
tools when fitting batteries and take extreme care not to short terminals when
working on them.
All DC Load cables terminate to the connectors at the front of the unit as shown in Figure 5.
These terminals are all 6mm
2
. Load connections are of a ‘push in’ design and cables can be
simply pushed into the connector for termination after stripping to the appropriate length.
Removal requires a small screwdriver to be inserted into the rectangular hole above the
connector whilst pulling on the cable.
Connector designators are available on the pull-out guide. See Figures 4, 5 and 6 for detail.
Fig 4 & 5, DC Connector detail and pullout guide
The battery cabling connects through the SB50 style power-pole connectors. From here it goes
directly to the appropriate circuit breaker, then via a Low Voltage Disconnect relay and current
shunt to the internal live bus. This can be seen in the appropriate wiring diagram as the rear of
this manual.
Note: Systems with only one battery breaker specified can be fitted with an additional load
breaker. Connection to the output from this breaker is made through the remaining SB50
power-pole.
Connector layout for PSX24042x1F-x00
Connector layout for PSX24051x1F-x00
Fig 6, DC Connector detail