7.2 reassembly

a.  refer to exploded view Figure 1.
b.  Prepare for installation of new packing by 

cleaning all packing chambers and glands 
of upper and lower gagecocks.

c.  Slip packing retainer on stem and install 

new packing.

d.  Thread stem assembly into gagecock by 

turning clockwise until stem seats and then 
back off one turn.

e.  assemble stem packing nut and tighten in 

place.

f.  assemble handwheel or lever, nameplate, 

and handwheel screw on stem and tighten 
securely into place.

g.  replace glass packing nut, glass packing 

gland and new glass packing on each end of 
tubular glass.

h.  With upper gagecock turned ⅛ turn 

counterclockwise from vertical, insert 
one end of sight glass into stuffing box 
connection in upper gagecock to sufficient 
depth to insure a clearance of lower 
gagecock glass packing nut.

i.  Tighten upper gagecock to original position 

holding sight glass in place with upward 
force to insure its clearing lower sight glass 
connection. check vertical alignment of 
gagecocks.

j.  Slide sight glass down into lower gagecock 

sight glass connection to a positive stop.

k.  Tighten glass packing nuts.
l.  close both gagecocks by turning handwheel 

or lever clockwise until stem seats.

m. replace guard rods.

refer to Section 5 for operation of gagecock 
when returned to service.

8 dIsPOsal at end Of useful lIfe

Penberthy gagecocks are used in a variety of 
fluid applications. By following the appropriate 
federal and industry regulations, the user 
must determine the extent of preparation and 
treatment the gagecock must incur before its 
disposal. a Material Safety Data Sheet (MSDS) 
may be required before disposal services 
accept certain components.
Metal, glass and polymers should be recycled 
whenever possible. refer to order and 
relevant technical data sheets for materials 
of construction.

9 telePhOne assIstanCe

If you are having difficulty with your Series N6 
gagecock, contact your local Penberthy 
distributor. You may also contact the factory 
direct at (956) 430-2500 and ask for an 
applications engineer. So that we may assist 
you more effectively, please have as much of 
the following information available as possible 
when you call:
∙ Model #
∙ Name of the company from whom you 

purchased your gagecock

∙ Invoice # and date
∙ Process conditions (pressure, flow rates, 

tank shape, etc)

∙ a brief description of the problem
∙ Trouble shooting procedures that failed

If attempts to solve your problem fail, you may 
request to return your gagecock to the factory 
for intensive testing. You must obtain a return 
authorization (r.a.) number from Emerson 
before returning anything. Failure to do so will 
result in the unit being returned to you without 
being tested, freight collect. To obtain an r.a. 
number, the following information (in addition 
to that above) is needed:
∙ reason for return
∙ Person to contact at your company
∙ 'Ship-to' address

There is a minimum charge for evaluation 
of non-warranty units. You will be contacted 
before any repairs are initiated should the cost 
exceed the minimum charge. If you return a 
unit under warranty, but it is not defective, the 
minimum charge will apply.

Summary of Contents for PENBERTHY N6 Series

Page 1: ...r products buildings personnel or property by reason of the installation or use of its products This is Emerson s sole warranty and in lieu of all other warranties expressed or implied which are hereby excluded including in particular all warranties of merchantability or fitness for a particular purpose This document and the warranty contained herein may not be modified and no other warranty expre...

Page 2: ...being gaged tends to surge in a rapid manner the ball checks could tend to give a false level reading or seat accidentally Series N6 gagecocks are not suitable for steam water applications unless they are furnished with one of the following optional features 1 Non automatic gagecocks ball checks removed from both upper and lower gagecocks 2 Automatic gagecocks vertical rising ball check and ball i...

Page 3: ...Under no circumstances should these design ratings or application data be exceeded Exceeding design ratings or application data may cause severe physical injury or property damage 3 2 User s rating inspection The user should confirm that 1 The gagecock set model number and pressure temperature rating stamped on nameplate 163 conforms to the description on the user s purchase order 2 The operating ...

Page 4: ...nstallation Guard rods two required are assembled downward through upper gagecock with swaged portion on rods at the top Bottoms of rods are positioned into respective holes in the lower gagecock 5 Operation 5 1 Pre operational check 1 Assure that all installation procedures have been completed 2 Check to determine that all connections are pressure tight 5 2 Hydrostatic test 1 Take all precautions...

Page 5: ...seat surface follow Disassembly steps a through f Renew seat by using a fine lapping compound and a mandrel with the same size shape and seat angle as the stem Flush gagecock body clean and reassemble by following steps a through f of Reassembly Note Series N6 gagecocks have an integral seat The gagecock body must be replaced when the seat becomes worn or damaged beyond repair 3 Signs of leakage a...

Page 6: ... appropriate federal and industry regulations the user must determine the extent of preparation and treatment the gagecock must incur before its disposal A Material Safety Data Sheet MSDS may be required before disposal services accept certain components Metal glass and polymers should be recycled whenever possible Refer to order and relevant technical data sheets for materials of construction 9 T...

Page 7: ...11 Body 15 Ball 17 Stem 18 Retainer stem packing 25 Packing stem 26 Nut stem packing 28 Handwheel 163 Nameplate 100 Screw Recommended spare parts Item Description Min qty 18 Retainer stem packing 2 25 Packing stem 2 26 Nut stem packing 1 34 Packing glass 2 35 Retainer glass packing 2 37 Nut glass packing 1 48 Glass 1 Recommended maximun quantities should provide spare parts for 10 of the gagecocks...