Type OSE

OPERATION

The pressure of the zone to be protected (generally the pipe 
line on the outlet side of the pressure regulator and situated 
after the slam shut valve) activates the safety manometric 
box BMS.

If pressure rises above the release set point the release 
relay frees the valve plug (key 7).

Through the action of the weight of the valve plug, the 
closing spring and the 

fl

 uid (attempting to close), the valve 

plug will seat into the ori

fi

 ce (key 6).

The gas 

fl

 ow is obstructed until the mechanism box is 

manually rearmed.

To reopen the valve plug an equal pressure balance on inlet 
and outlet sides is required.

The mechanism box is rearmed after opening the internal 
bypass (key 1).

Rearming and balancing are achieved at the same time.

INSTALLATION

!

AVERTISSEMENTS

All interventions on the equipment should 
only be performed by quali

fi

 ed and 

trained personnel.

C51

Figure 4

. Type OSE LS - Principle of Operation

The slam shut valve is installed on the 
inlet side of the regulator, on the horizontal 
pipeline. The mechanism box should be 
situated on top (see above schematic) or on 
top for versions DN 25-50-80.

Installation according to EN12186 is recommended.

Install according to direction of the 

fl

 uid 

fl

 ow 

(see arrow).

When assembling with adjacent elements, 
care must be taken not to create pressure 
force on the body and the assembling 
elements (bolts, O-rings, 

fl

 anges) should be 

compatible with the geometry and working 
conditions of the equipment.

If the case arises a support must be used to 
avoid pressure force on the body (a support 
can be installed under the 

fl

 anges).

Connect the safety manometric box (IS) to 
the impulse at 4D on the outlet pipe.

It is recommended to install an isolation 
valve (R1) and an atmospheric valve (R2), which 
can be useful for tripping and veri

fi

 cations.

No modi

fi

 cation should be made to the 

structure of the equipment (drilling, grinding, 
soldering ...).

Verify that the inlet side is protected by an 
appropriate device(s) to avoid exceeding the 
limits of utilization (PS, TS).

Summary of Contents for OSE Series

Page 1: ...eter Tube interior Ø 8 10 mm Safety contact See D103683X012 manual INTRODUCTION Scope of Manual This manual provides installation start up maintenance and parts ordering information for the Type OSE Slam Shut Valve Information on other equipment used with this slam shut valve is found in separate manuals Product Description The OSE Slam Shut Valve protects transmission and distribution networks or...

Page 2: ...ay travel mm 35 35 50 50 50 C50 Table 2 Flow Coefficient ΔP max Relay travel Figure 2 Label for Type OSE Slam Shut Valve OPERATING PRESSURE Body valve plug PS 100 bar maxi Associated BMS 1 according to size PSD 10 à 100 bar Maximum Inlet Pressure Pumax 100 bar Type DS Differential strength 2 OPERATING TEMPERATURE 3 TS 20 60 C 30 71 C SLAM SHUT Sizes available DN 25 50 80 100 150 Norm EN 14382 Oper...

Page 3: ...0 62 334 220 124 17 50 20 150 254 76 346 220 152 26 50 300 267 83 346 220 165 29 100 600 287 83 346 220 165 32 80 20 150 298 95 380 220 190 43 50 300 318 105 380 220 210 48 100 600 337 105 380 220 210 55 100 20 150 353 114 420 220 229 74 50 300 368 127 420 220 154 82 100 600 394 137 420 220 273 98 150 20 150 451 140 424 220 357 150 50 300 473 159 424 220 357 166 100 600 508 178 424 220 357 202 C53...

Page 4: ...ciple of Operation The slam shut valve is installed on the inlet side of the regulator on the horizontal pipeline The mechanism box should be situated on top see above schematic or on top for versions DN 25 50 80 Installation according to EN12186 is recommended Install according to direction of the fluid flow see arrow When assembling with adjacent elements care must be taken not to create pressur...

Page 5: ...be checked periodically COMMISSIONING WARNING All interventions on the equipment should only be performed by qualified and trained personnel Preliminary verifications Start up positions Inlet and outlet valves Closed Verify absence of pressure between inlet and outlet valves Slam shut valve plug Closed Impulse isolation valve Closed Impulse atmospheric valve Open Setpoint Verification Using the at...

Page 6: ...frequency Every 4 to 6 years or less depending on operating conditions In the case of BMS 162 or 071 it is highly recommended to check the condition of the diaphragm once yearly Verification Condition of O rings diaphragm and lubrication Replacement O rings diaphragm Tools Spanners 10 13 six sided wrench 6 Spanners According to DN size Francel spanner ref 197125 bypass and pin disassembly Valve pl...

Page 7: ...k the valve plug or contact after sales If the valve closes Operating correctly Observe the evolution of the outlet pressure check tightness If the outlet pressure in the slam shut is decreases External leak Locate and seal the leak or contact after sales If the outlet pressure in the slam shut is constant Bleed off the outlet side of the regulator Observe the evolution of the outlet pressure chec...

Page 8: ...972 548 3574 Asia Pacific Shanghai 201206 China Tel 86 21 2892 9000 Europe Bologna 40013 Italy Tel 39 051 419 0611 Middle East and Africa Dubai United Arab Emirates Tel 971 4811 8100 For further information visit www emersonprocess com regulators Natural Gas Technologies Emerson Process Management Regulator Technologies Inc USA Headquarters McKinney Texas 75070 USA Tel 1 800 558 5853 Outside U S 1...

Reviews: