1 storage and handling

1.1 Protection

Keystone butterfly valves are delivered with 
protection in accordance with the Keystone 
engineering Instructions, to protect the valve 
seats and disc from damage. Wrapping and/or 
covers should be left in place until immediately 
before fitting to the pipe.

1.2 storage

When valves are to be stored for some time 
(2 months or more) before being fitted, 
storage should be in the original delivery 
crates or cases.

Please read these instructions carefully

Hazard potentials:
• disregarding of instructions
• improper use of product
• insufficiently qualified personnel

valve application to be within the pressure/
temperature limits indicated in the P/t diagram.

essential points and functions of the valve 
should be inspected on a regular basis.

emerson.com/FinalControl

1.3 handling

1.3.1 Packed valves

lifting and handling of the packed valves in 
crates should be carried out by appropriate 
lifting equipment. If a fork lift truck is used, 
appropriate fork hitches are required.
the lifting and handling of packed valves in 
cases will be carried out in the lifting points.
the transportation of all packed material 
should be carried out safely and according 
the local safety regulations.

imPortant

Before valves are being installed or used 
the following actions are recommended.
1.  Valves/parts have to be inspected and 

thoroughly cleaned if required.

2.  Rubber parts need to be greased with silicone 

grease if not present anymore.

3.  All surfaces in contact with seats have to be 

thoroughly cleaned and greased with silicone 
grease if stored for more than 5 months.

recommendations

1.  temperature: storage temperature below 

25°C, above 0°C preferable below 15°C.

2.  Humidity: storage conditions should be such 

that condensation does not occur, store in 
a dry environment. Maximal 50% relative 
humidity.

3.  light: valve rubbers should be protected 

from light, in particular direct sunlight or 
strong artificial light with high ultra violet.

4.  Ozone: storage rooms should not 

contain any equipment generating ozone. 
e.g. lamps, electric motors.

1.2.1 Storage conditions

the valves should be stored off the ground 
in a clean, dry indoor area.
Protect the valve from temperature and 
humidity extremes, and exposure to excessive 
dust, moisture, vibration, deformations, 
sunlight and ozone.

1.3.2 Unpacked valves

the lifting and the handling of these valves has 
to be carried out by using appropriate means 
and by respecting the carrying limits. the 
handling must, preferably, be carried out on 
pallets, protecting the machined surfaces and 
seat to avoid damage.
When lifting the large dimension valves, the 
sling and the hooking of the load must be 
carried out by using the appropriate tools 
(brackets, hook, fasteners) and load balancing 
tools in order to prevent the valves from falling 
or moving during the lifting and handling.
the valve may be lifted only by slings attached 
to the flange holes or valve body; never to the 
actuator or the valve opening.

Before installation these instructions must be fully read and understood

© 2017 emerson. all rights reserved.

VCiom-00770-en 17/10

Summary of Contents for Keystone

Page 1: ...o be greased with silicone grease if not present anymore 3 All surfaces in contact with seats have to be thoroughly cleaned and greased with silicone grease if stored for more than 5 months Recommendations 1 Temperature storage temperature below 25 C above 0 C preferable below 15 C 2 Humidity storage conditions should be such that condensation does not occur store in a dry environment Maximal 50 r...

Page 2: ...ersonnel making any adjustments to the valves should utilize suitable equipment All required personal protection means should be worn 2 The line must be depressurized before installing the valve 3 Personnel trained in all aspects of manual and mechanical handling techniques only must carry out handling of the valves 4 Misuse of the valve is not allowed For example the valve handles actuators or ot...

Page 3: ...c travels clockwise to close Keystone Butterfly valves ParaSeal Installation and maintenance instructions Important Mating flange faces should be in good condition and free of dirt and or inclusions Both pipe insides to be well cleaned 2 5 3 Thermal A If the valve is used in applications with a fluid temperature above 40 C the outside of the body might be hot Sufficient measurements should be take...

Page 4: ... the actuation 4 Secure the disc with proper lifting equipment 5 Remove the bottom plug or cover 6 Remove the nut of the thru bolt at bottom hub 7 Mark the position of the bottom shaft and of the driving shaft versus the disc 8 Pull the driving shaft and belonging thru bolt out off body and disc If required use threaded hole in stemhead Support shaft and disc during removal It is possible that als...

Page 5: ...bolt 11 Snap ring 12 Key Parts list Part Name 1 Body 2 Disc 3 Driving top shaft 4 Bottom shaft 5 Seat 6 Bearing 7 Nut spring washer 8 Plug 9 Seal 10 Thru bolt 11 Bushing Parts list Part Name 1 Body 2 Disc 3 Driving top shaft 4 Bottom shaft 5 Seat 6 Bearing 7 Nut spring washer 8 Plug 9 Seal 10 Thru bolt 11 Key Keystone Butterfly valves ParaSeal Installation and maintenance instructions ...

Page 6: ...bility for the selection use or maintenance of any product Responsibility for proper selection use and maintenance of any product remains solely with the purchaser and end user Keystone is a mark owned by one of the companies in the Emerson Automation Solutions business unit of Emerson Electric Co Emerson Automation Solutions Emerson and the Emerson logo are trademarks and service marks of Emerson...

Reviews: