Electrical System Tests
P
RELIMINARY
I
NSPECTION
To prepare the system for initial power-up, run preliminary inspections as listed below:
(1)
Check that the system is disconnected from the main supply;
(2)
Inspect all electrical and mechanical connections visually for mechanical damage and for integrity
of components and accessories;
(3)
Check that the enclosure has been positioned as required under "Location" on Page 19;
(4)
Inspect incoming cables to ensure proper phase sequence (L1-L2-L3 clockwise);
(5)
Inspect Mains CTs wiring for proper phase and polarity marking and for proper connection into the
terminal block as required under "Mains CTs Connection" on Page 21;
(6)
Pull-test all control wiring to ensure secure seating in terminals;