2.6 General and Environmental Specifications
3.0 Installation
3.1 Preplanning the Installation
There is no substitute for planning the installation prior to beginning the work. Several minutes in planning
may save an hour or more during the installation. The following is a list of the factors to consider:
•
Location of Pump Module must be within 50' of the laundry machine.
•
Locate the Pump Module at a convenient height for pump tube servicing.
•
Allow room underneath the Pump Module for the optional Flush Manifold when planning flush
•
tc. Use appropriate hardware for each mounting surface, e.g. metal anchors in cement or cinder
•
uld
•
er or other convenient location so that the
operator can easily see the screen and operate the buttons. Allow space on the right side and bottom of
e access.
3.2
d probes.
ces, a 50' (15.24 meter) cable may be ordered.
•
Optional Flush Manifold.
•
Optional controller swivel mount bracket.
installations.
The Pump Module must be mounted to a solid surface , e.g., drywall, masonry, wood, cement, cinder
block, e
block.
Verify access to the appropriate power source for the unit. A separate power supply is desirable , but
you may have to use the laundry washer power. If an external switch or circuit breaker is used, it sho
be located as close as possible to the Pump Module.
•
The outlet supply tubing run should not exceed 50' (15.24 meters). The total input and output tubing
runs should be kept to less than 60’ (18.3 meters) or tubing durability will be affected.
The Controller must be mounted securely to the laundry wash
the controller for cable connections and future cabl
Materials Ordered Separately
•
Product pickup and output supply tubing, an
•
For long Controller to Pump Module distan
Advanced Laundry Control System Installation & Operation Manual
12